Permit Details

Permit Search

Permit

New Residential Construction

21839 SW STATE ROAD 47
FORT WHITE, FL 32038

Permit #
000039288
Application #
44410
Status Completed
  1. Submitted —
  2. Issued Feb 12, 2020
  3. Expires Mar 22, 2021
  4. Completed Sep 23, 2020

Property

Parcel #
04232-011
Owner
Donald & Jane Wilkinson
Acres
2.00
Subdivision
—
Zoning
A-3
Flood zone
X
District
2

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
1' ABOVE ROAD
Fema map number
12023C0488C
This is the construction of a
Single Family Dwelling
Setbacks Front
30
Setback Side 1
25
Setback Side 2
25
Setbacks Rear
25
Stories
1
Heated Area (Sqft)
1417
Total Area (Sqft)
1885
Building Height
16
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
Single family
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
20-0078

Status & Review History

  1. Zoning Review - On Hold
  2. Zoning Review - Completed/Sent for Final Review
  3. Permit Issued

Contractors

This is an owner-builder project.

Inspections

  1. Feb 25, 2020

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Need Porti Potti On Site Before Next Inspection.

    Inspected by Tommy Matthews

  2. Mar 10, 2020

    Passed: Building - Monolithic Slab

    Inspected by Tommy Matthews

  3. Mar 10, 2020

    Passed: Engineering - Setbacks

    Inspected by Tommy Matthews

  4. Mar 24, 2020

    Passed: Electrical - Temporary Service

    Need Elevation Letter Asap.

    Inspected by Tommy Matthews

  5. Mar 24, 2020

    Release to power company

    Inspected by Tommy Matthews

  6. Apr 7, 2020

    Passed: Building - Framing

    Inspected by Matt Forsyth

  7. May 8, 2020

    Passed: Electrical - 2nd Rough-In

    Inspected by Tommy Matthews

  8. May 8, 2020

    Passed: Mechanical - Rough In

    Inspected by Tommy Matthews

  9. May 8, 2020

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Tommy Matthews

  10. May 8, 2020

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Tommy Matthews

  11. May 13, 2020

    Septic Release Inspection

    Inspected by Health Dept

  12. May 29, 2020

    Failed: Building - Insulation

    Holes Where Electrical Wire Goes Through Top Plate Need To Be Sealed In All Locations.

    Inspected by Tommy Matthews

  13. Jun 1, 2020

    Passed: Building - Insulation

    Inspected by Troy Crews

  14. Aug 19, 2020

    Failed: Electrical - Permanent Power

    Must Have Elevation Confirmation From Surveyor Prior To Any More Inspections. Britt Is Working On This 9.11.20-lh - Letter Rec'd 9.14.20

    Inspected by Troy Crews

  15. Sep 14, 2020

    Passed: Electrical - Permanent Power

    Inspected by Matt Forsyth

  16. Sep 14, 2020

    Release to power company

    Inspected by Matt Forsyth

  17. Sep 22, 2020

    Failed: Building - Final

    Need Blower Door Test And Final Termite Treatment

    Inspected by Matt Forsyth

  18. Sep 23, 2020

    Passed: Building - Final

    Inspected by Matt Forsyth