567 NW HIGH POINTE DRLAKE CITY, FL 32055
Aaron Simque
Aaron Simque Homes Inc
County License & State License & Liability Insurance & Workers Comp Expired.
Ryan C Beville
Rbi Electrical Contracting Llc
Ralph W Laverdure
Rwl Roofing,llc.
Roger Whiddon
Lake City Plumbing Inc
Stephen M Brisbois
Epic Ac Service
Failed: Building - Footer
No Plans Or Permit On Site
Inspected by Tommy Matthews
Failed: Engineering - Setbacks
No Plans
Passed: Building - Footer
Inspected by Troy Crews
Passed: Engineering - Setbacks
Passed: Plumbing/Gas - 1st Underground Rough–In
Passed: Building - Slab
Failed: Building - Roof Decking
Not Ready.
Failed: Building - Ext Strapping/Wall Sheathing
Not Complete. Gables Not Ready. No Strapping Installed. Porch Columns Not Installed With Strapping. Make Sure Engineering Plans Are Available.
Passed: Plumbing/Gas - 2nd Rough-In
Failed: Mechanical - Rough In
Not Complete
Cancelled: Electrical - 1st Underground Rough–In
Passed: Building - Wall Sheathing
Failed: Building - Strapping
Front Porch Post Not Strapped
Check Areas Above Bonus Room
Cancelled: Building - Ext Strapping/Wall Sheathing
Failed: Building - Framing
Check Strapping On Double Girder Trusses
Failed: Electrical - 2nd Rough-In
Can Lights Disconnected In Master Bathroom And Open Wiring In Ceiling
Passed: Building - Framing
Can Lights Still Disconnected In North East Bathroom
Passed: Mechanical - Rough In
Cancelled: Plumbing/Gas - 2nd Rough-In
Passed: Building - Strapping
Passed: Building - Insulation
Passed: Electrical - 2nd Rough-In
Failed: Building - Slab
Prior To Approval, Need Structural Change Revision By Engineer. Need Porti Potti On Site. Need Correct Permit On Site. This Request Was Not The Correct Site Location. Termite Spray Not Approved. For Wrong Location.
Failed: Electrical - Permanent Power
No Conduit Out Of Meter Can, Need Garage Doors, Need Final Drive Approval And Septic Approval.
Cancelled: Building - Slab
Wrong Permit #
Passed: Electrical - Permanent Power
Electric Panel Lock Temporarily Also Need Final Driveway Release And Final Septic Release
Septic Release Inspection
Inspected by Health Dept
Release to power company
Inspected by Melissa Garber
Failed: Building - Final
Bad Receptacle In Garage And Waiting On Blower Door Test-rec'd
Inspected by Matt Forsyth
Passed: Building - Final
Waiver Permit 39134 Finaled 8/13/20-lh