Permit Details

Permit Search

Permit

New Residential Construction

445 SW FOREST GLN
LAKE CITY, FL 32025

Permit #
000038954
Application #
44027
Status Completed
  1. Submitted —
  2. Issued Dec 2, 2019
  3. Expires Nov 22, 2020
  4. Completed May 26, 2020

Property

Parcel #
09116-119
Owner
Hughes David Iii & Gloria E
Acres
5.01
Subdivision
Hills At Rose Creek Phase 1
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
1' ABOVE ROAD
Fema map number
12023C0384D
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
30
Setback Side 1
25
Setback Side 2
25
Setbacks Rear
25
Stories
1
Heated Area (Sqft)
2055
Total Area (Sqft)
3141
Building Height
26
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0834

Status & Review History

  1. Point Review - Completed/Sent for Plan Review
  2. Zoning Review - Completed/Sent for Final Review
  3. Permit Issued

Contractors

  • Bryan Zecher

    Bryan Zecher Construction Inc

    License
    CBC054575
    Title
    Cert.building Contractor
    Role
    Contractor
  • Marcus Matthews

    Matthews Electric Llc

    License
    EC13005459
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Anthony R Franks

    Franks & Lane Heating And Air, Llc

    License
    CAC1818631
    Title
    Cert. A/c Class “b”
    Role
    Subcontractor

    County License & State License Expired.

  • Cody Barrs

    Barrs Plumbing,inc.

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Robert Ogles Ii

    Ogles Roofing & Construction Llc

    License
    CCC1328699
    Title
    Cert Roofing
    Role
    Subcontractor

    County License & State License Expired.

Inspections

  1. Dec 10, 2019

    Passed: Building - Footer

    Inspected by Troy Crews

  2. Dec 10, 2019

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. Dec 10, 2019

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  4. Dec 10, 2019

    Release to power company

    Inspected by Troy Crews

  5. Jan 8, 2020

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Troy Crews

  6. Jan 10, 2020

    Passed: Building - Slab

    Garage Not Included

    Inspected by Tommy Matthews

  7. Jan 16, 2020

    Passed: Building - Monolithic Slab

    Porch And Garage

    Inspected by Troy Crews

  8. Jan 16, 2020

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  9. Jan 16, 2020

    Passed: Building - Slab

    Inspected by Troy Crews

  10. Feb 13, 2020

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  11. Feb 13, 2020

    Passed: Building - Framing

    Inspected by Troy Crews

  12. Feb 13, 2020

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  13. Feb 28, 2020

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  14. Feb 28, 2020

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  15. Feb 28, 2020

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  16. Mar 6, 2020

    Passed: Building - Insulation

    Inspected by Troy Crews

  17. Apr 21, 2020

    Passed: Electrical - Permanent Power

    Need Final Septic

    Inspected by Troy Crews

  18. Apr 22, 2020

    Release to power company

    Inspected by Laurie Hodson

  19. Apr 22, 2020

    Septic Release Inspection

    Inspected by Health Dept

  20. May 22, 2020

    Failed: Building - Final

    Step Down From House To Garage Over Maximum Height

    Inspected by Troy Crews

  21. May 26, 2020

    Passed: Building - Final

    Garage Step Corrected

    Inspected by Troy Crews