Permit Details

Permit Search

Permit

New Residential Construction

236 NW TAYLOR MAGEE PL
LAKE CITY, FL 32055

Permit #
000038875
Application #
43991
Status Completed
  1. Submitted Nov 6, 2019
  2. Issued Nov 7, 2019
  3. Expires Nov 15, 2020
  4. Completed May 21, 2020

Property

Parcel #
04800-115
Owner
Rivers Bill Anothy
Acres
1.59
Subdivision
Pines Of Falling Creek
Zoning
PRD
Flood zone
X
District
1

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
134'
Fema map number
12023C0195D
This is the construction of a
Single Family Dwelling
Setbacks Front
30
Setback Side 1
25
Setback Side 2
25
Setbacks Rear
25
Stories
1
Heated Area (Sqft)
2250
Total Area (Sqft)
3328
Building Height
21
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
SINGLE FAMILY DWELLING
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0642

Status & Review History

  1. Zoning Review - Completed/Sent for Final Review
  2. Permit Issued
  3. Point Review - Status Cleared

Contractors

  • Bryan Zecher

    Bryan Zecher Homes Inc

    License
    CBC1257343
    Title
    Building Contractor
    Role
    Contractor
  • Marcus Matthews

    Matthews Electric Llc

    License
    EC13005459
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Anthony R Franks

    Franks & Lane Heating And Air, Llc

    License
    CAC1818631
    Title
    Cert. A/c Class “b”
    Role
    Subcontractor

    County License & State License Expired.

  • Cody Barrs

    Barrs Plumbing,inc.

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Robert Ogles Ii

    Ogles Roofing & Construction Llc

    License
    CCC1328699
    Title
    Cert Roofing
    Role
    Subcontractor

    County License & State License Expired.

Inspections

  1. Nov 25, 2019

    Passed: Building - Footer

    Inspected by Tommy Matthews

  2. Nov 25, 2019

    Passed: Engineering - Setbacks

    Inspected by Tommy Matthews

  3. Nov 27, 2019

    Passed: Electrical - Temporary Service

    Inspected by Tommy Matthews

  4. Nov 27, 2019

    Release to power company

    Inspected by Tommy Matthews

  5. Dec 13, 2019

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Troy Crews

  6. Dec 17, 2019

    Passed: Building - Slab

    Elevation Letter Rec'd At 134.29'-12/17/19(lh)

    Inspected by Matt Forsyth

  7. Dec 31, 2019

    Passed: Building - Monolithic Slab

    Inspected by Troy Crews

  8. Dec 31, 2019

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  9. Dec 31, 2019

    Passed: Building - Slab

    Inspected by Troy Crews

  10. Jan 24, 2020

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Matt Forsyth

  11. Jan 24, 2020

    Passed: Building - Roof Decking

    Inspected by Matt Forsyth

  12. Jan 28, 2020

    Passed: Building - Framing

    Inspected by Tommy Matthews

  13. Feb 14, 2020

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  14. Feb 14, 2020

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  15. Feb 14, 2020

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  16. Feb 18, 2020

    Passed: Building - Insulation

    Inspected by Tommy Matthews

  17. Apr 8, 2020

    Passed: Electrical - Permanent Power

    Need Septic Release

    Inspected by Matt Forsyth

  18. Apr 20, 2020

    Release to power company

    Rec'd. Eh

    Inspected by Matt Forsyth

  19. Apr 20, 2020

    Septic Release Inspection

    Inspected by Health Dept

  20. May 19, 2020

    Passed: Building - Final

    Inspected by Tommy Matthews

  21. May 21, 2020

    Certificate-Release Certificate

    5.19.20

    Inspected by T. Matthews