Permit Details

Permit Search

Permit

New Residential Construction

332 SW STONERIDGE DR
LAKE CITY, FL 32024

Permit #
000038874
Application #
43910
Status Completed
  1. Submitted Oct 29, 2019
  2. Issued Nov 7, 2019
  3. Expires Dec 29, 2020
  4. Completed Jul 2, 2020

Property

Parcel #
03406-109
Owner
Zack Paulk
Acres
2.50
Subdivision
Rose Creek Plantation Phase 1
Zoning
A-3
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0383D
This is the construction of a
Single Family Dwelling
Setbacks Front
30
Setback Side 1
25
Setback Side 2
25
Setbacks Rear
25
Stories
1
Heated Area (Sqft)
3120
Total Area (Sqft)
4426
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
SINGLE FAMILY DWELLING
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0748

Status & Review History

  1. Point Review - Received
  2. Zoning Review - Completed/Sent for Final Review
  3. Permit Issued

Contractors

  • Seth A. Heitzman

    Seth Heitzman Construction,inc.

    License
    CBC1251065
    Title
    Building Contractor
    Role
    Contractor

    County License & State License & Liability Insurance & Workers Comp Expired.

  • Marcus Matthews

    Matthews Electric Llc

    License
    EC13005459
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Rodney L Cribbs

    Quality Air Care Llc

    License
    RA13067616
    Title
    Cert. A/c Class “b”
    Role
    Subcontractor

    County License & State License & Liability Insurance Expired.

  • Cody Barrs

    Barrs Plumbing,inc.

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Robert Ogles Ii

    Ogles Roofing & Construction Llc

    License
    CCC1328699
    Title
    Cert Roofing
    Role
    Subcontractor

    County License & State License Expired.

Inspections

  1. Nov 26, 2019

    Passed: Building - Footer

    Inspected by Matt Forsyth

  2. Nov 26, 2019

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  3. Dec 11, 2019

    Passed: Electrical - Temporary Service

    Inspected by Matt Forsyth

  4. Dec 18, 2019

    Passed: Electrical - 1st Underground Rough–In

    Inspected by Matt Forsyth

  5. Dec 18, 2019

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Matt Forsyth

  6. Dec 19, 2019

    Rescheduled 12/20/2019:Building - Slab

    Inspected by Matt Forsyth

  7. Dec 20, 2019

    Passed: Building - Slab

    Inspected by Troy Crews

  8. Dec 27, 2019

    Release to power company

    Inspected By Matt...

    Inspected by Mf 12.11.19

  9. Jan 10, 2020

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Matt Forsyth

  10. Jan 10, 2020

    Cancelled: Building - Framing

    Inspected by Matt Forsyth

  11. Jan 24, 2020

    Passed: Building - Framing

    Inspection Was For Roof Sheathing Only

    Inspected by Matt Forsyth

  12. Feb 5, 2020

    Passed: Building - Framing

    Building Envelope Framing Complete

    Inspected by Matt Forsyth

  13. Feb 7, 2020

    Passed: Electrical - 2nd Rough-In

    Inspected by Matt Forsyth

  14. Feb 7, 2020

    Passed: Mechanical - Above Ceiling

    Inspected by Matt Forsyth

  15. Feb 7, 2020

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Matt Forsyth

  16. Jun 10, 2020

    Passed: Electrical - Permanent Power

    Need Septic Release

    Inspected by Matt Forsyth

  17. Jun 12, 2020

    Release to power company

    Inspected by Melissa Garber

  18. Jun 12, 2020

    Septic Release Inspection

    Inspected by Health Dept

  19. Jul 2, 2020

    Passed: Building - Final

    Inspected by Matt Forsyth