Status Completed
  1. Submitted Oct 16, 2019
  2. Issued Oct 16, 2019
  3. Expires Aug 22, 2020
  4. Completed Feb 26, 2020

Property

Parcel #
08111-111
Owner
Russ & Kelly Papka
Acres
0.98
Subdivision
Holly Hill
Zoning
RSF-2
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0292D
This is the construction of a
Single Family Dwelling
Setbacks Front
25
Setback Side 1
10
Setback Side 2
10
Setbacks Rear
15
Stories
1
Heated Area (Sqft)
1610
Total Area (Sqft)
2089
Building Code Construction Type
V
Building Code Element
B
Occupancy Use Title
SINGLE FAMILY DWELLING
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0750

Status & Review History

  1. Permit Issued

Contractors

  • Adam R Papka

    Adam's Construction Llc

    License
    CBC1253409
    Title
    Building Contractor
    Role
    Contractor

    County License & State License & Liability Insurance & Workers Comp Expired.

  • Donald Davis

    High Springs Electric Inc.

    License
    EC0002306
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Clinton G Wilson

    Wilson Heat & Air,inc.

    License
    CAC057886
    Title
    Class B A/c
    Role
    Subcontractor
  • Mark B Barrs

    Barrs Plumbing,inc.

    License
    CFC057219
    Title
    Plumbing Contractor
    Role
    Subcontractor

    County License & State License Expired.

  • Caleb Laughlin

    Precision Exteriors,llc.

    License
    CCC1327718
    Title
    Roofing Contractor
    Role
    Subcontractor

    County License & State License & Liability Insurance Expired.

Inspections

  1. Oct 18, 2019

    Passed: Electrical - Temporary Service

    Inspected by Matt Forsyth

  2. Oct 18, 2019

    Release to power company

    Inspected by Matt Forsyth

  3. Oct 21, 2019

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Troy Crews

  4. Oct 23, 2019

    Passed: Building - Monolithic Slab

    Inspected by Troy Crews

  5. Oct 23, 2019

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  6. Nov 18, 2019

    Passed: Building - Roof Decking

    Inspected by Matt Forsyth

  7. Dec 3, 2019

    Failed: Building - Framing

    Need Simpson Stud Plate Connectors

    Inspected by Matt Forsyth

  8. Dec 3, 2019

    Passed: Electrical - 2nd Rough-In

    Inspected by Matt Forsyth

  9. Dec 3, 2019

    Passed: Mechanical - Above Ceiling

    Inspected by Matt Forsyth

  10. Dec 3, 2019

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Matt Forsyth

  11. Dec 6, 2019

    Passed: Building - Framing

    Inspected by Matt Forsyth

  12. Dec 6, 2019

    Passed: Building - Insulation

    Inspected by Matt Forsyth

  13. Jan 29, 2020

    Septic Release Inspection

    Inspected by Health Dept

  14. Feb 10, 2020

    Passed: Electrical - Permanent Power

    Inspected by Matt Forsyth

  15. Feb 10, 2020

    Release to power company

    Inspected by Matt Forsyth

  16. Feb 20, 2020

    Failed: Building - Final

    No Water Pressure On Guest Bathroom Toilet And Sink

    Inspected by Matt Forsyth

  17. Feb 24, 2020

    Passed: Building - Final

    Inspected by Matt Forsyth