Permit Details

Permit Search

Permit

New Residential Construction

336 SW WOODLEAF CT
LAKE CITY, FL 32024

Permit #
000038590
Application #
42579
Status Completed
  1. Submitted Sep 12, 2019
  2. Issued Sep 12, 2019
  3. Expires Sep 1, 2020
  4. Completed Mar 5, 2020

Property

Parcel #
02438-134
Owner
Mf Butler Homes, Llc
Acres
0.51
Subdivision
Emerald Cove
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0290D
This is the construction of a
SFD/UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
1880.00
Total Area (Sqft)
2557.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0617

Status & Review History

No status updates yet.

Contractors

  • Mark Bauer

    License
    CBC1259633
    Title
    —
    Role
    —

    County License & State License Expired.

Inspections

  1. Sep 13, 2019

    Passed: Building - Footer

    Need Porti Potti Before Next Inspection

    Inspected by Tommy Matthews

  2. Sep 13, 2019

    Passed: Engineering - Setbacks

    Inspected by Tommy Matthews

  3. Sep 24, 2019

    Passed: Electrical - Temporary Service

    Sent To Power Comp In error By Inspector

    Inspected by Tommy Matthews

  4. Sep 24, 2019

    Release to power company

    Inspected by Tommy Matthews

  5. Sep 26, 2019

    Passed: Electrical - 1st Underground Rough–In

    Inspected by Matt Forsyth

  6. Sep 26, 2019

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Need Elevation At Slab Letteron Next Inspection

    Inspected by Matt Forsyth

  7. Oct 1, 2019

    Release to power company

    Inspected by Tm

  8. Oct 1, 2019

    Passed: Building - Slab

    Inspected by Tommy Matthews

  9. Oct 15, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  10. Oct 31, 2019

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  11. Nov 14, 2019

    Passed: Building - Framing

    Inspected by Matt Forsyth

  12. Nov 14, 2019

    Passed: Electrical - 2nd Rough-In

    Inspected by Matt Forsyth

  13. Nov 14, 2019

    Passed: Mechanical - Above Ceiling

    Inspected by Matt Forsyth

  14. Nov 14, 2019

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Matt Forsyth

  15. Nov 18, 2019

    Passed: Building - Insulation

    Wall Insulation Only

    Inspected by Matt Forsyth

  16. Jan 16, 2020

    Passed: Electrical - Permanent Power

    Inspected by Tommy Matthews

  17. Jan 24, 2020

    Release to power company

    Inspected by Mg

  18. Jan 24, 2020

    Septic Release Inspection

    Inspected by Health Dept

  19. Mar 5, 2020

    Passed: Building - Final

    Inspected by Troy Crews

  20. Mar 5, 2020

    Certificate-Release Certificate

    Inspected by Troy Crews