Permit Details

Permit Search

Permit

New Residential Construction

376 SW DAISY RD
LAKE CITY, FL 32024

Permit #
000038582
Application #
42556
Status Completed
  1. Submitted Sep 9, 2019
  2. Issued Sep 9, 2019
  3. Expires Aug 16, 2020
  4. Completed Feb 19, 2020

Property

Parcel #
00467-010
Owner
Nathan Brown
Acres
4.93
Subdivision
—
Zoning
AG-3
Flood zone
X
District
2

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0370C
This is the construction of a
SFD, UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
1514.00
Total Area (Sqft)
1649.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0655

Status & Review History

No status updates yet.

Contractors

  • Amanda Senea

    License
    CRC1329482
    Title
    —
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Sep 17, 2019

    Passed: Building - Footer

    Inspected by Matt Forsyth

  2. Sep 17, 2019

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  3. Oct 1, 2019

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Matt Forsyth

  4. Oct 3, 2019

    Passed: Electrical - Temporary Service

    Inspected by Matt Forsyth

  5. Oct 3, 2019

    Release to power company

    Inspected by Matt Forsyth

  6. Oct 7, 2019

    Passed: Building - Slab

    Inspected by Matt Forsyth

  7. Nov 5, 2019

    Cancelled: Building - Framing

    Inspected by Matt Forsyth

  8. Nov 6, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Matt Forsyth

  9. Nov 12, 2019

    Passed: Building - Roof Decking

    Inspected by Matt Forsyth

  10. Nov 26, 2019

    Passed: Building - Roof Decking

    Inspected by Matt Forsyth

  11. Nov 26, 2019

    Passed: Electrical - 2nd Rough-In

    Inspected by Matt Forsyth

  12. Nov 26, 2019

    Passed: Mechanical - Above Ceiling

    Inspected by Matt Forsyth

  13. Nov 26, 2019

    Passed: Mechanical - Rough In

    Inspected by Matt Forsyth

  14. Nov 26, 2019

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Matt Forsyth

  15. Dec 2, 2019

    Passed: Building - Insulation

    Walls Only

    Inspected by Matt Forsyth

  16. Feb 6, 2020

    Cancelled: Electrical - Temporary Service

    Inspected by Matt Forsyth

  17. Feb 6, 2020

    Passed: Mechanical - Above Ceiling

    Inspected by Matt Forsyth

  18. Feb 6, 2020

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Matt Forsyth

  19. Feb 6, 2020

    Failed: Electrical - Permanent Power

    Need Underground Conduit And Septic Release

    Inspected by Matt Forsyth

  20. Feb 12, 2020

    Septic Release Inspection

    Inspected by Health Dept

  21. Feb 12, 2020

    Passed: Electrical - Permanent Power

    Inspected by Matt Forsyth

  22. Feb 12, 2020

    Release to power company

    Inspected by Matt Forsyth

  23. Feb 18, 2020

    Passed: Building - Final

    Inspected by Matt Forsyth

  24. Feb 18, 2020

    Passed: Building - Insulation

    Inspected by Matt Forsyth