Permit Details

Permit Search

Permit

New Commercial Construction

4784 W US HIGHWAY 90
LAKE CITY, FL 32055

Permit #
000038490
Application #
42427
Status Completed
  1. Submitted Aug 19, 2019
  2. Issued Aug 19, 2019
  3. Expires Jun 9, 2020
  4. Completed Dec 12, 2019

Property

Parcel #
02460-001
Owner
Trenton Medical Ctr Inc/palms Medical
Acres
0.83
Subdivision
—
Zoning
CHI
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0290D
This is the construction of a:
REMODEL/ADDITION
Driveway access to property:
Existing Drive
Is there a Fire Sprinkler System?
No
Setbacks Front
20.00
Setback Rear
15.00
Stories
1
Total Area (Sqft)
1050.00
Building Code Construction Type
IV
Building Code Element
B
Building Code Occupancy Types
Business
Occupancy Use Title
Medical Office
Dev Permit #
F023-
Design Occupant Load
54
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
X

Status & Review History

No status updates yet.

Contractors

  • Keith Lemmon

    License
    CBC1259328
    Title
    —
    Role
    —

    Liability Insurance & Workers Comp Expired.

Inspections

  1. Aug 20, 2019

    Passed: Mechanical - Rough In

    Main Trunk Lines Only To Wrap

    Inspected by Troy Crews

  2. Aug 28, 2019

    Rescheduled 8/30/2019:Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  3. Aug 30, 2019

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  4. Sep 11, 2019

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  5. Sep 11, 2019

    Release to power company

    Inspected by Troy Crews

  6. Sep 20, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    North And East Walls

    Inspected by Troy Crews

  7. Sep 20, 2019

    Passed: Fire - Fire Rated Wall

    Discussed Mezzanine Walls

    Inspected by Troy Crews

  8. Oct 1, 2019

    Passed: Building - Framing

    Inspected by Troy Crews

  9. Oct 1, 2019

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  10. Oct 1, 2019

    Passed: Electrical - Above Ceiling

    Inspected by Troy Crews

  11. Oct 1, 2019

    Passed: Mechanical - Above Ceiling

    Inspected by Troy Crews

  12. Oct 1, 2019

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  13. Oct 1, 2019

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Troy Crews

  14. Oct 1, 2019

    Passed: Plumbing/Gas - Water Pipe

    Inspected by Troy Crews

  15. Oct 8, 2019

    Passed: Building - Insulation

    Inspected by Troy Crews

  16. Oct 31, 2019

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  17. Oct 31, 2019

    Release to power company

    Inspected by Troy Crews

  18. Dec 11, 2019

    Passed: Building - Final

    Inspected by Troy Crews

  19. Dec 12, 2019

    Passed: Fire - Fire Final

    Inspected by Tad Cervantes