Permit Details

Permit Search

Permit

New Residential Construction

178 SW NEWLYWED CT
LAKE CITY, FL 32024

Permit #
000038482
Application #
42415
Status Completed
  1. Submitted Aug 16, 2019
  2. Issued Aug 16, 2019
  3. Expires Jul 7, 2020
  4. Completed Jan 16, 2020

Property

Parcel #
02973-103
Owner
Bullard Management
Acres
0.57
Subdivision
Hunnington Place
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0293D
This is the construction of a
SFD/UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
1669.00
Total Area (Sqft)
2369.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0561

Status & Review History

No status updates yet.

Contractors

  • Adam Papka

    License
    CBC1253409
    Title
    —
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Aug 29, 2019

    Passed: Electrical - Temporary Service

    Inspected by Tommy Matthews

  2. Aug 29, 2019

    Release to power company

    Inspected by Tommy Matthews

  3. Sep 16, 2019

    Cancelled: Building - Monolithic Slab

    Inspected by Troy Crews

  4. Sep 16, 2019

    Cancelled: Engineering - Setbacks

    Inspected by Troy Crews

  5. Sep 17, 2019

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  6. Sep 18, 2019

    Passed: Building - Monolithic Slab

    Inspected by Troy Crews

  7. Sep 18, 2019

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  8. Oct 10, 2019

    Failed: Building - Roof Decking

    Shiners In Numerous Places. Need To Be Removed And Renailed.

    Inspected by Tommy Matthews

  9. Oct 15, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  10. Oct 15, 2019

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  11. Oct 18, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Matt Forsyth

  12. Oct 18, 2019

    Failed: Building - Framing

    9 Foot Window Opening Needs 2 X 12 Header. Water Pipe In Garage Needs Shield Plates In 2 Spots

    Inspected by Matt Forsyth

  13. Oct 18, 2019

    Passed: Electrical - 2nd Rough-In

    Inspected by Matt Forsyth

  14. Oct 18, 2019

    Passed: Mechanical - Rough In

    Inspected by Matt Forsyth

  15. Oct 18, 2019

    Failed: Plumbing/Gas - 2nd Rough-In

    Need Shield Plates In Garage

    Inspected by Matt Forsyth

  16. Oct 18, 2019

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Matt Forsyth

  17. Oct 23, 2019

    Failed: Building - Framing

    Shield Plates Still Not Installed On Cold Water Line In 2 Places In Garage

    Inspected by Matt Forsyth

  18. Oct 23, 2019

    Passed: Building - Insulation

    Inspected by Matt Forsyth

  19. Dec 9, 2019

    Failed: Electrical - Permanent Power

    Need Garage Door Installed Protect Panel Box Along With Exterior Door Lock

    Inspected by Matt Forsyth

  20. Dec 12, 2019

    Failed: Electrical - Permanent Power

    Need Garage Door. Need Septic And Driveway Approval

    Inspected by Tommy Matthews

  21. Dec 20, 2019

    Passed: Electrical - Permanent Power

    Need Septic Release

    Inspected by Matt Forsyth

  22. Dec 27, 2019

    Release to power company

    Inspected by Mg

  23. Dec 27, 2019

    Septic Release Inspection

    Bdt Rec'd 1.8.2020

    Inspected by Health Dept

  24. Jan 9, 2020

    Passed: Building - Final

    Inspected by Tommy Matthews