Permit Information

New Commercial Construction Permit

Address 1771 NW LAKE JEFFERY RD
LAKE CITY, FL 32055
Parcel #: 02284-102
Acres:5.00
Owner:Concept Development Inc
Subdivision:Crs Bascom Norris At Lake Jeffery
Zoning:CI
Flood Zone:X
District:1
Application #:42331
Permit #: 000038430
Related Permit:
Submitted:Friday, August 2, 2019
Issued:Friday, August 2, 2019
Expires:Friday, November 8, 2019
Completed:Friday, November 8, 2019
Status: Completed
Septic Release? Yes

Notes

MINIMUM FLOOR ELEVATION PER SDP IS 178', NEED ELEVATION CONFIRMATION LETTER AT SLAB, NOC ON FILE ELEVATION LETTER RECIEVED 178.06

Job Details

Finished floor requirement
Fema map number 12023C0283D
This is the construction of a: DOLLAR GENERAL STORE
Driveway access to property: Culvert Waiver
Is there a Fire Sprinkler System? No
Setbacks Front 20.00
Setback Side 1 15.00
Setback Side 2 15.00
Setback Rear 5.00
Stories 1
Heated Area (Sqft) 9100.00
Total Area (Sqft) 9100.00
Building Height 19
Building Code Construction Type II
Building Code Element B
Building Code Occupancy Types Mercantile
Occupancy Use Title Retail Store
Dev Permit # F023-
Design Occupant Load 137
Building Code Edition Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000) X-CITY

Review Notes

Contractors

Name / Business License Title Role
Brian Scott Crawford

Liability Insurance & Workers Comp & Employees Workers Comp Expired.
CGC1515491

Inspections

Inspection Notes Performed By Date
Passed: Electrical - Rough In Troy Crews 8/14/2019
Passed: Plumbing/Gas - Rough In Troy Crews 8/14/2019
Failed: Building - Footer Covered In Water Troy Crews 8/19/2019
Passed: Engineering - Setbacks Troy Crews 8/19/2019
Passed: Building - Footer Troy Crews 8/21/2019
Passed: Engineering - Setbacks Troy Crews 8/21/2019
Passed: Building - Slab Troy Crews 8/21/2019
Passed: Electrical - Footer Steel & Grounding Troy Crews 8/21/2019
Passed: Building - Vertical Cells/Columns Troy Crews 9/5/2019
Passed: Building - Lintel/Tie Beam Troy Crews 9/5/2019
Passed: Building - Framing Troy Crews 9/27/2019
Passed: Electrical - 2nd Rough-In Troy Crews 9/27/2019
Passed: Mechanical - Rough In Troy Crews 9/27/2019
Passed: Plumbing/Gas - 2nd Rough-In Troy Crews 9/27/2019
Passed: Building - Monolithic Slab Troy Crews 10/3/2019
Passed: Engineering - Setbacks Troy Crews 10/3/2019
Cancelled: Engineering - Final Driveway 8/2/19 David Mccormick Failed. Need To Purchase A Culvert Permit And Install. Laurie Hodson 10/9/2019
Failed: Electrical - Permanent Power Need Building Secured Door Locks, Completion Of Front Entry Glass, Wire Nut All Open Conductors Troy Crews 10/10/2019
Passed: Electrical - Permanent Power Need Elevation Letter For Release Troy Crews 10/14/2019
Failed: Building - Lintel/Tie Beam No Further Inspections Until Stamped Letter Received On Elevation. Note No Inspections This Area In Afternoon. Troy Crews 10/16/2019
Passed: Building - Lintel/Tie Beam Dumpster Enclosure Troy Crews 10/17/2019
Passed: Building - Masonry Wall Reinforcing Troy Crews 10/17/2019
Release to power company 10/22/2019
Passed: Electrical - Permanent Power Final In Building Troy Crews 10/30/2019
Passed: Mechanical - Performance Test and Balance Troy Crews 10/30/2019
Passed: Plumbing/Gas - Sanitary Troy Crews 10/30/2019
Passed: Building - Final Release Pending Fire Final, And Zoning Final Troy Crews 11/1/2019
Passed: Engineering - Zoning Final Initial Inspection Failed Due To Two Missing Oak Trees And Fire Hydrant Not In Approved Location. Applicant Applied For A Minor Modification To An Approved Site Plan For The Relocation Of The Fire Hydrant. Fire Department Approved New Location On November 6, 2019. Two Missing Oak Trees Have Been Planted. Engineer Final Complete Brandon Stubbs 11/6/2019
Passed: Fire - Fire Final Per Tad - He Does Need To Measure Shelving-lh 11/7/19 Tad Cervantes 11/7/2019
Passed: Fire - Fire Final Shelving Egress Tad Cervantes 11/8/2019

Contact Us

Building Department

Office Hours

Monday-Friday
8:00 A.M. - 4:30 P.M.

Contact Information

Phone: 386-758-1008
Fax: 386-758-2160

Email: bldginfo@columbiacountyfla.com

Location

135 NE Hernando Ave.
Lake City, FL 32055 (opens in new window)

Mailing Address

P.O. Box 1529
Lake City, FL 32056-1529

Public Records

Public records policy and fees

Board of County Commissioners
Tel. (386) 758-1326
Fax: (386) 758-2182
Email: publicrecords@columbiacountyfla.com

Mailing Address:
P.O. Box 1529
Lake City, FL 32056-1529

Citizen Feedback

Let us know how we're doing

ADA Accessibility

Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the Columbia County ADA Coordinator at (386) 758-3344. You may also email that office at hr@columbiacountyfla.com and provide a brief description of the inaccessible feature.

Columbia County strives to provide reasonable accommodations to help people with disabilities have an equal opportunity to participate in our public meetings. Please notify our ADA Coordinator at least 48 hours prior to the public meeting by calling (386) 758-3344.