Permit Details

Permit Search

Permit

New Commercial Construction

2618 SW SISTERS WELCOME RD
LAKE CITY, FL 32025

Permit #
000038427
Application #
42323
Status Completed
  1. Submitted Aug 1, 2019
  2. Issued Aug 1, 2019
  3. Expires Jan 16, 2021
  4. Completed Jul 23, 2020

Property

Parcel #
02952-005
Owner
Spell Properties Of North Fl Llc
Acres
10.00
Subdivision
—
Zoning
CI
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0293D
This is the construction of a:
COMM. METAL BLDG/UTL
Driveway access to property:
Existing Drive
Is there a Fire Sprinkler System?
No
Setbacks Front
20.00
Setback Side 1
5
Setback Side 2
5
Setback Rear
15.00
Stories
1
Total Area (Sqft)
9000.00
Building Height
30
Building Code Construction Type
II
Building Code Element
A
Building Code Occupancy Types
Factory
Occupancy Use Title
Service & Storage
Dev Permit #
F023-
Design Occupant Load
18
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0558

Status & Review History

No status updates yet.

Contractors

  • David Simque

    License
    CGC1516165
    Title
    —
    Role
    —

    County License & State License & Liability Insurance Expired.

Inspections

  1. Aug 1, 2019

    Septic Release Inspection

    Inspected by Health Dept

  2. Sep 27, 2019

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Troy Crews

  3. Oct 1, 2019

    Passed: Building - Slab

    Inspected by Troy Crews

  4. Jan 13, 2020

    Passed: Building - Footer

    Inspected by Troy Crews

  5. Jan 13, 2020

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  6. Jan 13, 2020

    Passed: Building - Monolithic Slab

    Inspected by Troy Crews

  7. Jun 17, 2020

    Passed: Building - Framing

    Inspected by Troy Crews

  8. Jun 17, 2020

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  9. Jun 17, 2020

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  10. Jun 17, 2020

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  11. Jul 2, 2020

    Passed: Electrical - Permanent Power

    Need Elevation Letter For Release

    Inspected by Troy Crews

  12. Jul 14, 2020

    Release to power company

    Elevation Letter Rec'd

    Inspected by Laurie Hodson

  13. Jul 15, 2020

    Release to power company

  14. Jul 15, 2020

    Rescheduled 7/17/2020:Fire - Fire Final

    Inspected by Troy Crews

  15. Jul 15, 2020

    Rescheduled 7/17/2020:Building - Final

    Inspected by Troy Crews

  16. Jul 15, 2020

    Rescheduled 7/17/2020:Engineering - Zoning Final

    Inspected by Troy Crews

  17. Jul 15, 2020

    Passed: Engineering - Zoning Final

    Site Inspection Finish - Passed

    Inspected by Brandon Stubbs

  18. Jul 17, 2020

    Passed: Building - Final

    Pending Fire Department Final

    Inspected by Troy Crews

  19. Jul 17, 2020

    Rescheduled 7/20/2020:Fire - Fire Final

    Inspected by Troy Crews

  20. Jul 20, 2020

    Passed: Fire - Fire Final

    Ok Pertad 7-23-20

    Inspected by Troy Crews

  21. Jul 23, 2020

    Certificate-Release Certificate

    Inspected by Troy Crews