Permit Details

Permit Search

Permit

New Residential Construction

331 SW KICKLIGHTER TER
LAKE CITY, FL 32024

Permit #
000038186
Application #
40959
Status Completed
  1. Submitted Jun 4, 2019
  2. Issued Jun 4, 2019
  3. Expires Apr 15, 2020
  4. Completed Oct 22, 2019

Property

Parcel #
02953-001
Owner
Joseph & Eva Martino
Acres
18.86
Subdivision
—
Zoning
RR
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0293D
This is the construction of a
SFD/UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
2597.00
Total Area (Sqft)
3606.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0383

Status & Review History

No status updates yet.

Contractors

  • Blake Lunde, Ii.

    License
    CBC1253408
    Title
    —
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Jun 5, 2019

    Passed: Building - Footer

    Inspected by Troy Crews

  2. Jun 5, 2019

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. Jun 18, 2019

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Matt Forsyth

  4. Jun 24, 2019

    Rescheduled 6/25/2019:Building - Slab

    Needed Moved To Next Day

    Inspected by Laurie Hodson

  5. Jun 26, 2019

    Passed: Building - Slab

    Inspected by Troy Crews

  6. Jul 22, 2019

    Passed: Building - Roof Decking

    Inspected by Matt Forsyth

  7. Jul 22, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Matt Forsyth

  8. Aug 1, 2019

    Passed: Building - Framing

    Inspected by Troy Crews

  9. Aug 1, 2019

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  10. Aug 1, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  11. Aug 9, 2019

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  12. Aug 20, 2019

    Passed: Building - Insulation

    Inspected by Troy Crews

  13. Sep 20, 2019

    Passed: Electrical - Permanent Power

    Need Health Release

    Inspected by Troy Crews

  14. Sep 24, 2019

    Release to power company

    Inspected by Lh

  15. Sep 24, 2019

    Septic Release Inspection

    Inspected by Health Dept

  16. Oct 18, 2019

    Passed: Building - Final

    Inspected by Troy Crews