New Residential Construction

217 SW UPSTAGE GLEN
LAKE CITY, FL 32024

Permit #
000038049
Application #
40761
Status Completed
  1. Submitted Apr 29, 2019
  2. Issued Apr 29, 2019
  3. Expires Jul 27, 2020
  4. Completed Jan 31, 2020

Property

Parcel #
09280-149
Owner
James David Waller & Alica Waller
Acres
4.51
Subdivision
The Oaks Of Lake City
Zoning
PRRD
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0395C
This is the construction of a
SFD, UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
3473.00
Total Area (Sqft)
5397.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0277

Status & Review History

No status updates yet.

Contractors

  • Isaiah Cully

    License
    CBC1259655
    Title
    —
    Role
    —

Inspections

  1. May 8, 2019

    Passed: Building - Footer

    Inspected by Troy Crews

  2. May 8, 2019

    Passed: Engineering - Setbacks

    Noc To Us In Morning Per Contractor

    Inspected by Troy Crews

  3. May 8, 2019

    Passed: Electrical - Footer Steel & Grounding

    Inspected by Troy Crews

  4. May 15, 2019

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  5. May 21, 2019

    Passed: Building - Slab

    Inspected by Troy Crews

  6. Jul 29, 2019

    Passed: Building - Framing

    Draft Stop Wall Cavity Ar Vaulted Ceiling An Second Story Wall, Also Nail Off Post To Beam Front Porch

    Inspected by Troy Crews

  7. Jul 29, 2019

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  8. Jul 29, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  9. Aug 28, 2019

    Passed: Mechanical - Rough In

    Inspected by Tommy Matthews

  10. Aug 28, 2019

    Passed: Electrical - Rough In

    Inspected by Tommy Matthews

  11. Aug 28, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Tommy Matthews

  12. Sep 16, 2019

    Passed: Building - Insulation

    Inspected by Troy Crews

  13. Jan 23, 2020

    Failed: Electrical - Permanent Power

    Need Garage Doors Installed And I Release The Driveway

    Inspected by Matt Forsyth

  14. Jan 24, 2020

    Septic Release Inspection

    Inspected by Health Dept

  15. Jan 24, 2020

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  16. Jan 24, 2020

    Release to power company

    Inspected by Troy Crews

  17. Jan 29, 2020

    Passed: Building - Final

    Release Pending Blower Door Test, Rec'd 1/31/20

    Inspected by Troy Crews