Status Completed
  1. Submitted Apr 26, 2019
  2. Issued Apr 26, 2019
  3. Expires Feb 25, 2020
  4. Completed Sep 3, 2019

Property

Parcel #
08107-044
Owner
Mike Roberts & Tris Roberts,(jtwrs)
Acres
0.87
Subdivision
Edgewood Estates
Zoning
RSF-2
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0292D
This is the construction of a
SFD/UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
1508.00
Total Area (Sqft)
2330.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0533

Status & Review History

No status updates yet.

Contractors

  • James H. Johnston

    License
    CRC1328128
    Title
    —
    Role
    —

    County License & State License & Liability Insurance & Workers Comp & Employees Workers Comp Expired.

Inspections

  1. Apr 29, 2019

    Passed: Electrical - Temporary Service

    Released Again. Clay Didn't receive. 04.30.19-(jlw)

    Inspected by Tommy Matthews

  2. Apr 29, 2019

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Tommy Matthews

  3. Apr 30, 2019

    Passed: Building - Slab

    Inspected by Tommy Matthews

  4. May 14, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Matt Forsyth

  5. May 28, 2019

    Passed: Building - Framing

    Inspected by Tommy Matthews

  6. May 28, 2019

    Passed: Electrical - Rough In

    Inspected by Tommy Matthews

  7. May 28, 2019

    Passed: Mechanical - Rough In

    Inspected by Tommy Matthews

  8. May 28, 2019

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Tommy Matthews

  9. May 28, 2019

    Passed: Plumbing/Gas - Water Pipe

    Inspected by Tommy Matthews

  10. May 31, 2019

    Passed: Building - Insulation

    Inspected by Tommy Matthews

  11. Jul 30, 2019

    Septic Release Inspection

    Inspected by Health Dept

  12. Aug 7, 2019

    Passed: Electrical - Permanent Power

    Inspected by Tommy Matthews

  13. Aug 7, 2019

    Release to power company

    Inspected by Tommy Matthews

  14. Aug 29, 2019

    Passed: Building - Final

    Inspected by Tommy Matthews