Permit Details

Permit Search

Permit

New Residential Construction

145 SW OLD PECAN CT
LAKE CITY, FL 32024

Permit #
000038014
Application #
40711
Status Completed
  1. Submitted Apr 23, 2019
  2. Issued Feb 28, 2020
  3. Expires Feb 3, 2021
  4. Completed Aug 7, 2020

Property

Parcel #
02439-137
Owner
Gary Sorensen
Acres
0.26
Subdivision
The Reserve At Jewel Lake
Zoning
PRD
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0290D
This is the construction of a
SFD/UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
1673.00
Total Area (Sqft)
2256.00
Building Height
20
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
SINGLE FAMILY DWELLING
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
X-CITY

Status & Review History

  1. Permit Renewed

Contractors

  • Milton Smith, Sr.

    License
    CBC1254161
    Title
    —
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Mar 6, 2020

    Passed: Building - Footer

    Inspected by Troy Crews

  2. Mar 6, 2020

    Passed: Engineering - Setbacks

    15 Ft Setback Line Outside Brick Wall Per Milton

    Inspected by Troy Crews

  3. Mar 20, 2020

    Failed: Plumbing/Gas - 1st Underground Rough–In

    Water Line Blew Out.

    Inspected by Troy Crews

  4. Mar 23, 2020

    Passed: Building - Slab

    Inspected by Troy Crews

  5. Mar 23, 2020

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Pipe Repaired Pressure On Lines

    Inspected by Troy Crews

  6. Apr 21, 2020

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  7. Apr 21, 2020

    Passed: Building - Wall Sheathing

    Inspected by Troy Crews

  8. Apr 30, 2020

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  9. May 4, 2020

    Passed: Building - Framing

    Inspected by Troy Crews

  10. May 7, 2020

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  11. May 13, 2020

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  12. May 19, 2020

    Passed: Building - Insulation

    Inspected by Troy Crews

  13. Jun 16, 2020

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  14. Jun 16, 2020

    Release to power company

    Inspected by Troy Crews

  15. Aug 7, 2020

    Passed: Building - Final

    Inspected by Troy Crews