Permit Details

Permit Search

Permit

New Residential Construction

15838 N US HIGHWAY 441
WHITE SPRINGS, FL 32096

Permit #
000037784
Application #
40366
Status Completed
  1. Submitted Feb 22, 2019
  2. Issued Feb 22, 2019
  3. Expires Apr 8, 2020
  4. Completed Oct 15, 2019

Property

Parcel #
04507-006
Owner
Corey & Kayla Hebert
Acres
13.61
Subdivision
—
Zoning
AG-1
Flood zone
X
District
—

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
This is the construction of a
SFD, UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
1978.00
Total Area (Sqft)
3158.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0085

Status & Review History

No status updates yet.

Contractors

  • Matt Hentzelman

    License
    CGC1514780
    Title
    —
    Role
    —

    County License & State License Expired.

Inspections

  1. Mar 12, 2019

    Passed: Building - Footer

    Inspected by Tommy Matthews

  2. Mar 12, 2019

    Passed: Engineering - Setbacks

    Inspected by Tommy Matthews

  3. Mar 29, 2019

    Release to power company

    Corrected Power Company

    Inspected by Lh

  4. Mar 29, 2019

    Passed: Electrical - Temporary Service

    Inspected by Matt Forsyth

  5. Mar 29, 2019

    Release to power company

    Inspected by Matt Forsyth

  6. Mar 29, 2019

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Matt Forsyth

  7. Mar 29, 2019

    Release to power company

    Inspected by Matt Forsyth

  8. Apr 11, 2019

    Passed: Building - Slab

    Inspected by Tommy Matthews

  9. May 30, 2019

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  10. May 30, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  11. Jul 9, 2019

    Failed: Building - Framing

    Truss Tg-2 Needs Strapping Call Back In Prior To Insulation

    Inspected by Troy Crews

  12. Jul 9, 2019

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  13. Jul 9, 2019

    Failed: Mechanical - Rough In

    Bath Fans Not Ducted, Range Vent Not Installed Call Back In Prior To Insulation

    Inspected by Troy Crews

  14. Jul 9, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  15. Jul 12, 2019

    Passed: Building - Framing

    Items Corrected

    Inspected by Troy Crews

  16. Jul 12, 2019

    Passed: Mechanical - Rough In

    Items Corrected

    Inspected by Troy Crews

  17. Jul 12, 2019

    Cancelled: Mechanical - Framing/Fire Damper

    Inspected by Troy Crews

  18. Jul 12, 2019

    Failed: Building - Insulation

    Not Complete

    Inspected by Troy Crews

  19. Jul 15, 2019

    Passed: Building - Insulation

    Inspected by Troy Crews

  20. Sep 5, 2019

    Septic Release Inspection

    Inspected by Health Dept

  21. Sep 6, 2019

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  22. Sep 6, 2019

    Release to power company

    Inspected by Troy Crews

  23. Oct 11, 2019

    Passed: Building - Final

    Inspected by Troy Crews