Permit Details

Permit Search

Permit

New Residential Construction

668 SW CHESTERFIELD CR
LAKE CITY, FL 32024

Permit #
000037746
Application #
40306
Status Completed
  1. Submitted Feb 14, 2019
  2. Issued Feb 14, 2019
  3. Expires Feb 23, 2020
  4. Completed Aug 27, 2019

Property

Parcel #
03117-140
Owner
Daniel & Janet Crapps
Acres
0.50
Subdivision
Crosswinds
Zoning
RSF-2
Flood zone
X
District
—

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
This is the construction of a
SFD/UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
1646.00
Total Area (Sqft)
2535.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0948

Status & Review History

No status updates yet.

Contractors

  • James M. Lipscomb

    License
    CBC1253543
    Title
    —
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Mar 11, 2019

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  2. Mar 15, 2019

    Failed: Building - Slab

    Verify One Foot Above Road

    Inspected by Tommy Matthews

  3. Mar 18, 2019

    Passed: Building - Monolithic Slab

    Inspected by Troy Crews

  4. Mar 18, 2019

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  5. May 28, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Matt Forsyth

  6. May 28, 2019

    Failed: Building - Framing

    Need Truss Engineering Completed

    Inspected by Matt Forsyth

  7. Jun 4, 2019

    Passed: Building - Framing

    Inspected by Matt Forsyth

  8. Jun 4, 2019

    Passed: Electrical - Rough In

    Inspected by Matt Forsyth

  9. Jun 4, 2019

    Passed: Mechanical - Rough In

    Inspected by Matt Forsyth

  10. Jun 4, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Matt Forsyth

  11. Jun 10, 2019

    Rescheduled 6/11/2019:Building - Insulation

    Inspected by Matt Forsyth

  12. Jun 11, 2019

    Passed: Building - Insulation

    Inspected by Matt Forsyth

  13. Aug 13, 2019

    Passed: Electrical - Permanent Power

    Corrected Type Of Inspection

    Inspected by Tommy Matthews

  14. Aug 15, 2019

    Septic Release Inspection

    Inspected by Health Dept

  15. Aug 15, 2019

    Release to power company

    Inspected by Tommy Matthews

  16. Aug 27, 2019

    Passed: Building - Final

    Inspected by Troy Crews