Permit Details

Permit Search

Permit

New Residential Construction

320 NW SCENIC LAKE DR
LAKE CITY, FL 32055

Permit #
000037550
Application #
40017
Status Completed
  1. Submitted Dec 17, 2018
  2. Issued Dec 17, 2018
  3. Expires Mar 11, 2020
  4. Completed Sep 16, 2019

Property

Parcel #
02270-001
Owner
Randy & Tina Mckenzie
Acres
2.40
Subdivision
—
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0280D
This is the construction of a
SFD/UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
3543.00
Total Area (Sqft)
4762.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0895

Status & Review History

No status updates yet.

Contractors

  • Bryan Zecher

    License
    CBC054575
    Title
    —
    Role
    —

Inspections

  1. Jan 17, 2019

    Passed: Electrical - Temporary Service

    Inspected by Tommy Matthews

  2. Jan 17, 2019

    Release to power company

    Inspected by Tommy Matthews

  3. Jan 22, 2019

    Passed: Building - Footer

    Get Compaction Test On Fill

    Inspected by Troy Crews

  4. Jan 22, 2019

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  5. Jan 22, 2019

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  6. Jan 22, 2019

    Release to power company

    Inspected by Troy Crews

  7. Feb 20, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  8. Feb 26, 2019

    Failed: Building - Slab

    Was Not Complete. Wire Mesh On Site But Not Installed. Other Items Not Complete.

    Inspected by Tommy Matthews

  9. Feb 27, 2019

    Passed: Building - Slab

    Inspected by Tommy Matthews

  10. Apr 12, 2019

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  11. Apr 12, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  12. Apr 23, 2019

    Passed: Building - Framing

    Inspected by Troy Crews

  13. May 13, 2019

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  14. May 13, 2019

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  15. May 13, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  16. May 28, 2019

    Passed: Building - Insulation

    Inspected by Tommy Matthews

  17. Aug 7, 2019

    Failed: Electrical - Permanent Power

    Need Locks On Glass Sliding Doors. Need Septicrelease. Need Driveway Approval.

    Inspected by Tommy Matthews

  18. Aug 12, 2019

    Septic Release Inspection

    Inspected by Health Dept

  19. Aug 13, 2019

    Passed: Electrical - Permanent Power

    Inspected by Tommy Matthews

  20. Aug 13, 2019

    Release to power company

    Inspected by Tommy Matthews

  21. Sep 13, 2019

    Passed: Building - Final

    Inspected by Tommy Matthews