Permit Details

Permit Search

Permit

New Residential Construction

385 SE RACETRACK LN
LAKE CITY, FL 32025

Permit #
000037463
Application #
39889
Status Completed
  1. Submitted Nov 21, 2018
  2. Issued Nov 21, 2018
  3. Expires Apr 18, 2020
  4. Completed Oct 21, 2019

Property

Parcel #
08631-006
Owner
Michael & Stephanie Foreman
Acres
40.50
Subdivision
—
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0313D
This is the construction of a
SFD/UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
2
Heated Area (Sqft)
4081.00
Total Area (Sqft)
6472.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0823

Status & Review History

No status updates yet.

Contractors

  • Bryan Zecher

    License
    CBC054575
    Title
    —
    Role
    —

Inspections

  1. Nov 27, 2018

    Passed: Building - Footer

    Inspected by Troy Crews

  2. Nov 27, 2018

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. Nov 27, 2018

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  4. Nov 27, 2018

    Release to power company

    Inspected by Troy Crews

  5. Jan 3, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  6. Jan 8, 2019

    Passed: Building - Slab

    Inspected by Tommy Matthews

  7. Jan 11, 2019

    Passed: Building - Footer

    Back Porch And Side Porch Pads

    Inspected by Troy Crews

  8. Jan 11, 2019

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  9. Feb 8, 2019

    Passed: Building - Roof Decking

    Inspected by Tommy Matthews

  10. Feb 12, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  11. Feb 15, 2019

    Passed: Building - Framing

    Inspected by Troy Crews

  12. Mar 8, 2019

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  13. Mar 8, 2019

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  14. Mar 8, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  15. Mar 27, 2019

    Passed: Building - Insulation

    Inspected by Tommy Matthews

  16. Jun 28, 2019

    Passed: Electrical - Permanent Power

    Need Health Release

    Inspected by Troy Crews

  17. Jul 2, 2019

    Release to power company

    Rec'd. Eh

    Inspected by Tc

  18. Jul 2, 2019

    Septic Release Inspection

    Inspected by Health Dept

  19. Oct 21, 2019

    Passed: Building - Final

    Inspected by Troy Crews