Permit Details

Permit Search

Permit

New Commercial Construction

14143 SOUTH US HWY 441 LAKE CITY FL 32024

Permit #
000037278
Application #
39655
Status Completed
  1. Submitted Oct 1, 2018
  2. Issued Oct 1, 2018
  3. Expires Aug 28, 2019
  4. Completed Mar 1, 2019

Property

Parcel #
09590-001
Owner
2511 Howell, Llc
Acres
0.83
Subdivision
—
Zoning
CHI
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0505C
This is the construction of a:
DUNKIN DONUTS REST
Driveway access to property:
D.O.T. Permit
Is there a Fire Sprinkler System?
No
Setbacks Front
20.00
Setback Side 1
5.00
Setback Side 2
5.00
Setback Rear
15.00
Stories
1
Heated Area (Sqft)
1325.00
Total Area (Sqft)
1460.00
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Mercantile
Occupancy Use Title
RESTAURANT
Dev Permit #
F023-
Design Occupant Load
38
Building Code Edition
Florida Building Code 2014 5th Edition & 2011 National Electrical Code
Septic# (00-0000) or (X00-000)
X-COUNTY

Status & Review History

No status updates yet.

Contractors

  • Ashley Rumble

    License
    CBC1257461
    Title
    —
    Role
    —

    County License & State License & Liability Insurance & Workers Comp & Employees Workers Comp Expired.

Inspections

  1. Oct 25, 2018

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  2. Oct 30, 2018

    Passed: Electrical - Underground Rough-In

    Under Ground Pvc

    Inspected by Troy Crews

  3. Nov 2, 2018

    Passed: Building - Slab

    Mono

    Inspected by Troy Crews

  4. Nov 26, 2018

    Release to power company

    Inspected by Troy Crews

  5. Nov 27, 2018

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  6. Nov 29, 2018

    Passed: Electrical - Underground Rough-In

    Secondary Conduits To Building

    Inspected by Troy Crews

  7. Dec 6, 2018

    Passed: Plumbing/Gas - Rough In

    2nd Rough

    Inspected by Troy Crews

  8. Dec 6, 2018

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  9. Dec 6, 2018

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  10. Dec 10, 2018

    Cancelled: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  11. Dec 12, 2018

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  12. Dec 20, 2018

    Failed: Building - Framing

    No One On Site ,no Complete Plans, Also Need Elevation Letter From Surveyor Prior To Any Further Inspections. 12-27-18 Elevation Survey Rec'd.

    Inspected by Troy Crews

  13. Jan 3, 2019

    Passed: Building - Framing

    Inspected by Troy Crews

  14. Jan 4, 2019

    Passed: Building - Lath/Stucco

    Inspected by Troy Crews

  15. Jan 10, 2019

    Passed: Building - Insulation

    Inspected by Troy Crews

  16. Jan 10, 2019

    Passed: Mechanical - Rough In

    Duct Rough In For Rooftop Units

    Inspected by Troy Crews

  17. Jan 23, 2019

    Rescheduled 1/24/2019:Electrical - Permanent Power

    Inspected by Troy Crews

  18. Jan 24, 2019

    Failed: Electrical - Permanent Power

    Need All Door Locks And D.o.t Approval

    Inspected by Troy Crews

  19. Jan 31, 2019

    Passed: Electrical - Permanent Power

    D.o.t Approval Required Prior To C.o.

    Inspected by Troy Crews

  20. Jan 31, 2019

    Release to power company

    Inspected by Troy Crews

  21. Feb 12, 2019

    Cancelled: Re-Roof - Final

    Inspected by Troy Crews

  22. Feb 13, 2019

    Passed: Building - Above Ceiling

    Inspected by Troy Crews

  23. Feb 13, 2019

    Passed: Electrical - Above Ceiling

    Inspected by Troy Crews

  24. Feb 13, 2019

    Passed: Mechanical - Above Ceiling

    Inspected by Troy Crews

  25. Feb 15, 2019

    Cancelled: Building - Above Ceiling

    Inspected by Troy Crews

  26. Feb 15, 2019

    Cancelled: Electrical - Above Ceiling

    Inspected by Troy Crews

  27. Feb 15, 2019

    Cancelled: Mechanical - Above Ceiling

    Inspected by Troy Crews

  28. Feb 18, 2019

    Cancelled: Electrical - Above Ceiling

    Inspected by Troy Crews

  29. Feb 18, 2019

    Cancelled: Electrical - Permanent Power

    Inspected by Troy Crews

  30. Feb 18, 2019

    Cancelled: Electrical - Service Upgrade Final

    Inspected by Troy Crews

  31. Feb 19, 2019

    Passed: Building - Final

    Need Site Final And Fire Final For C.o.

    Inspected by Troy Crews

  32. Feb 21, 2019

    Passed: Fire - Fire Final

    They Passed The Life Safety Inspection With Exception Of The Extinguishers Haven't Been Installed. They Should Be In The Next Couple Of Days. I Will Revisit The Site Next Week.

    Inspected by Tad Cervantes

  33. Feb 25, 2019

    Failed: Engineering - Zoning Final

    Required Fencing Around Retention Pond Was Not Installed.

    Inspected by Brandon Stubbs

  34. Mar 1, 2019

    Passed: Engineering - Zoning Final

    Inspected by Brandon Stubbs