Permit Details

Permit Search

Permit

New Residential Construction

251 SW BREEZY DR
LAKE CITY, FL 32025

Permit #
000037147
Application #
39416
Status Completed
  1. Submitted Aug 27, 2018
  2. Issued Aug 27, 2018
  3. Expires Nov 11, 2019
  4. Completed May 16, 2019

Property

Parcel #
08944-012
Owner
Dustin F. Mcmanus
Acres
5.11
Subdivision
Hillcrest Unrec
Zoning
AG-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0401C
This is the construction of a
SFD, UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
2184.00
Total Area (Sqft)
3600.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0693

Status & Review History

No status updates yet.

Contractors

  • Jason Elixson

    License
    CBC1250331
    Title
    —
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Sep 6, 2018

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  2. Sep 6, 2018

    Release to power company

    Inspected by Troy Crews

  3. Sep 12, 2018

    Passed: Building - Footer

    Inspected by Troy Crews

  4. Sep 12, 2018

    Passed: Engineering - Setbacks

    Reminder 1ft, Above Road

    Inspected by Troy Crews

  5. Oct 2, 2018

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  6. Oct 3, 2018

    Passed: Building - Slab

    Inspected by Troy Crews

  7. Nov 8, 2018

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  8. Dec 20, 2018

    Failed: Building - Framing

    Check Bracing A-02 And A-03 Truss, Anchor Bolts At Green Paint Spots, Add Nails Rear Porch Header Both Sides

    Inspected by Troy Crews

  9. Dec 20, 2018

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  10. Dec 20, 2018

    Failed: Mechanical - Rough In

    Attatch Bath Fan Duct East Side Bath

    Inspected by Troy Crews

  11. Dec 20, 2018

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  12. Dec 21, 2018

    Passed: Building - Framing

    Inspected by Troy Crews

  13. Dec 21, 2018

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  14. Jan 11, 2019

    Passed: Building - Insulation

    Inspected by Troy Crews

  15. Apr 17, 2019

    Passed: Electrical - Permanent Power

    Need Health Release

    Inspected by Troy Crews

  16. Apr 18, 2019

    Release to power company

    Inspected by Lh

  17. Apr 18, 2019

    Septic Release Inspection

    Inspected by Health Dept

  18. May 15, 2019

    Passed: Building - Final

    Inspected by Troy Crews