Permit Details

Permit Search

Permit

New Residential Construction

676 SW ROSEMARY DR
LAKE CITY, FL 32024

Permit #
000037141
Application #
39407
Status Completed
  1. Submitted Aug 27, 2018
  2. Issued Aug 27, 2018
  3. Expires Feb 3, 2020
  4. Completed Aug 21, 2019

Property

Parcel #
02731-122
Owner
Preserve At Laurel Lake Inc
Acres
0.46
Subdivision
Preserve @ Laurel Lake
Zoning
PRD
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0290D
This is the construction of a
SFD, UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
3196.00
Total Area (Sqft)
2246.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
X-CITY

Status & Review History

No status updates yet.

Contractors

  • Aaron Simque

    License
    R282811879
    Title
    —
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Sep 7, 2018

    Passed: Building - Footer

    Double Check North Setback On Rosemary

    Inspected by Troy Crews

  2. Sep 7, 2018

    Passed: Engineering - Setbacks

    Double Check North Setback On Rosemary For 25 Ft

    Inspected by Troy Crews

  3. Oct 3, 2018

    Passed: Plumbing/Gas - Underground Rough-In

    Waste Only Per Water Lines

    Inspected by Troy Crews

  4. Oct 15, 2018

    Passed: Building - Slab

    Special Foundation In Place

    Inspected by Troy Crews

  5. Oct 22, 2018

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  6. Dec 6, 2018

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  7. Jan 31, 2019

    Passed: Building - Framing

    Still Need Elevation Lettter

    Inspected by Troy Crews

  8. Jan 31, 2019

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  9. Jan 31, 2019

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  10. Jan 31, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  11. Feb 5, 2019

    Passed: Building - Insulation

    Rec'd Elevation Letter 2/8/19, Need Elevation Letter Prior To Any Further Inspections

    Inspected by Troy Crews

  12. Jun 18, 2019

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  13. Jun 18, 2019

    Release to power company

    Inspected by Troy Crews

  14. Aug 7, 2019

    Passed: Building - Final

    Release Pending Blower Door Test, Rec'd 8/20/19

    Inspected by Troy Crews