Permit Details

Permit Search

Permit

New Residential Construction

944 NW ZACK DR LAKE CITY FL 32055

Permit #
000037102
Application #
39352
Status Completed
  1. Submitted Aug 17, 2018
  2. Issued Aug 17, 2018
  3. Expires Aug 24, 2019
  4. Completed Feb 28, 2019

Property

Parcel #
02372-626
Owner
Art Mcquillan
Acres
0.51
Subdivision
Arbor Green @ Emerald Lakes
Zoning
RSF-2
Flood zone
X
District
—

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
This is the construction of a
SFD/UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
1741.00
Total Area (Sqft)
2518.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0603

Status & Review History

No status updates yet.

Contractors

  • Kevin L. Bedenbaugh, Jr.

    License
    CGC1516042
    Title
    —
    Role
    —

Inspections

  1. Aug 28, 2018

    Passed: Building - Footer

    Inspected by Tommy Matthews

  2. Aug 28, 2018

    Passed: Engineering - Setbacks

    Inspected by Tommy Matthews

  3. Sep 20, 2018

    Passed: Building - Slab

    Inspected by Tommy Matthews

  4. Oct 3, 2018

    Passed: Electrical - Temporary Service

    Inspected by Tommy Matthews

  5. Oct 3, 2018

    Release to power company

    Inspected by Tommy Matthews

  6. Oct 9, 2018

    Failed: Building - Ext Strapping/Wall Sheathing

    Check Spacing On Nail Pattern

    Inspected by Troy Crews

  7. Oct 9, 2018

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  8. Oct 10, 2018

    Passed: Building - Ext Strapping/Wall Sheathing

    Re-nailed

    Inspected by Troy Crews

  9. Oct 24, 2018

    Passed: Building - Framing

    Inspected by Troy Crews

  10. Oct 24, 2018

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  11. Oct 24, 2018

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  12. Oct 24, 2018

    Failed: Plumbing/Gas - Rough In

    Not Complete

    Inspected by Troy Crews

  13. Oct 29, 2018

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  14. Nov 5, 2018

    Passed: Building - Insulation

    Check On Dryer Vent

    Inspected by Troy Crews

  15. Jan 18, 2019

    Passed: Electrical - Permanent Power

    Need Health And Driveway. Drive Rec'd 1/24/19

    Inspected by Troy Crews

  16. Jan 24, 2019

    Release to power company

    Inspected by Laurie Hodson

  17. Jan 24, 2019

    Septic Release Inspection

    Inspected by Health Dept

  18. Feb 25, 2019

    Passed: Building - Final

    Inspected by Troy Crews