Permit Details

Permit Search

Permit

New Residential Construction

260 NE DWELLING PL LAKE CITY FL 32055

Permit #
000037062
Application #
39233
Status Completed
  1. Submitted Aug 6, 2018
  2. Issued Aug 6, 2018
  3. Expires Jul 13, 2019
  4. Completed Jan 18, 2019

Property

Parcel #
04842-113
Owner
L & L Development And Services, L.c.
Acres
0.50
Subdivision
Falling Creek Village
Zoning
RSF-MH-2
Flood zone
X
District
—

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
This is the construction of a
SFD/UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
1578.00
Total Area (Sqft)
2291.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0645

Status & Review History

No status updates yet.

Contractors

  • Bryan Zecher

    License
    CBC054575
    Title
    —
    Role
    —

Inspections

  1. Aug 16, 2018

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  2. Aug 16, 2018

    Release to power company

    Inspected by Troy Crews

  3. Aug 22, 2018

    Passed: Building - Footer

    Inspected by Troy Crews

  4. Aug 22, 2018

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  5. Aug 27, 2018

    Release to power company

    Corrected Power Company

    Inspected by Laurie Hodson

  6. Aug 30, 2018

    Passed: Plumbing/Gas - Rough In

    Inspected by Tommy Matthews

  7. Sep 7, 2018

    Passed: Building - Slab

    Inspected by Tommy Matthews

  8. Sep 21, 2018

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  9. Sep 27, 2018

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  10. Sep 27, 2018

    Passed: Building - Framing

    Inspected by Troy Crews

  11. Oct 5, 2018

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  12. Oct 5, 2018

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  13. Oct 5, 2018

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  14. Oct 15, 2018

    Passed: Building - Insulation

    Inspected by Tommy Matthews

  15. Nov 29, 2018

    Failed: Electrical - Permanent Power

    Need Garage Door Health Release And Driveway

    Inspected by Troy Crews

  16. Dec 6, 2018

    Passed: Electrical - Permanent Power

    Need Health And Drive. Drive Approved 12-6-18

    Inspected by Troy Crews

  17. Dec 14, 2018

    Release to power company

    Inspected by Laurie Hodson

  18. Dec 14, 2018

    Septic Release Inspection

    Inspected by Health Dept

  19. Jan 14, 2019

    Passed: Building - Final

    Blower Door Test Rec'd 5.46

    Inspected by Troy Crews