Status Completed
  1. Submitted Jul 10, 2018
  2. Issued Jul 10, 2018
  3. Expires Oct 6, 2019
  4. Completed Apr 12, 2019

Property

Parcel #
02940-012
Owner
Scott Randolph Bailey
Acres
6.01
Subdivision
—
Zoning
RSF-2
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0293D
This is the construction of a
SFD, UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
2012.00
Total Area (Sqft)
2894.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0504

Status & Review History

No status updates yet.

Contractors

  • Jason Elixson

    License
    CBC1250331
    Title
    —
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Jul 18, 2018

    Passed: Building - Footer

    Inspected by Troy Crews

  2. Jul 18, 2018

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. Aug 21, 2018

    Passed: Electrical - Temporary Service

    Inspected by Tommy Matthews

  4. Aug 21, 2018

    Release to power company

    Inspected by Tommy Matthews

  5. Aug 21, 2018

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Tommy Matthews

  6. Sep 27, 2018

    Passed: Building - Slab

    Inspected by Troy Crews

  7. Nov 8, 2018

    Failed: Building - Ext Strapping/Wall Sheathing

    Nailing Is Required To Be 4” In All Locations. It Is Not Consistently 4” As Required.

    Inspected by Tommy Matthews

  8. Nov 13, 2018

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Randy Jones

  9. Jan 9, 2019

    Cancelled: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  10. Jan 9, 2019

    Passed: Building - Framing

    Inspected by Troy Crews

  11. Jan 9, 2019

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  12. Jan 9, 2019

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  13. Jan 9, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  14. Jan 16, 2019

    Failed: Building - Insulation

    Wall Between Garage And Heated Area Is Not Insulated As Required

    Inspected by Tommy Matthews

  15. Jan 17, 2019

    Passed: Building - Insulation

    Inspected by Tommy Matthews

  16. Mar 5, 2019

    Failed: Electrical - Permanent Power

    Need Garage Doors ,door Locks, Final Septic, Final Driveway

    Inspected by Troy Crews

  17. Mar 19, 2019

    Septic Release Inspection

    Inspected by Health Dept

  18. Mar 20, 2019

    Passed: Electrical - Permanent Power

    Need Driveway Final

    Inspected by Troy Crews

  19. Mar 25, 2019

    Release to power company

    Lh

  20. Apr 9, 2019

    Passed: Building - Final

    Need Termite, Blower Door Test Results Rec'd - 3.88

    Inspected by Tommy Matthews