Status Completed
  1. Submitted Jun 1, 2018
  2. Issued Jun 1, 2018
  3. Expires May 26, 2019
  4. Completed Nov 30, 2018

Property

Parcel #
08920-110
Owner
Mf Butler Homes,llc
Acres
2.01
Subdivision
Briarwood
Zoning
PRRD
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0382D
This is the construction of a
SFD/UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
1871.00
Total Area (Sqft)
2557.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0399

Status & Review History

No status updates yet.

Contractors

  • Mark Bauer

    License
    CBC1259633
    Title
    —
    Role
    —

    County License & State License Expired.

Inspections

  1. Jun 13, 2018

    Passed: Building - Footer

    Inspected by Troy Crews

  2. Jun 13, 2018

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. Jun 22, 2018

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Tommy Matthews

  4. Jul 2, 2018

    Passed: Building - Slab

    Bait System For Termite

    Inspected by Troy Crews

  5. Jul 11, 2018

    Passed: Building - Ext Strapping/Wall Sheathing

    Walls Only

    Inspected by Troy Crews

  6. Jul 13, 2018

    Passed: Building - Roof Decking

    Partial South Half Call In Other Half

    Inspected by Troy Crews

  7. Jul 18, 2018

    Failed: Building - Roof Decking

    No More Done Since Last Partial

    Inspected by Troy Crews

  8. Jul 23, 2018

    Passed: Building - Roof Decking

    Partial

    Inspected by Randy Jones

  9. Jul 24, 2018

    Passed: Building - Roof Decking

    Inspected by Tommy Matthews

  10. Aug 9, 2018

    Passed: Building - Framing

    Still Need Elevation Letter, Rec'd 8/10/18

    Inspected by Troy Crews

  11. Aug 9, 2018

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  12. Aug 9, 2018

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  13. Aug 9, 2018

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  14. Aug 15, 2018

    Passed: Building - Insulation

    Inspected by Troy Crews

  15. Oct 1, 2018

    Passed: Electrical - Permanent Power

    Need Health Release

    Inspected by Troy Crews

  16. Oct 3, 2018

    Release to power company

    Inspected by Laurie Hodson

  17. Oct 3, 2018

    Septic Release Inspection

    Inspected by Health Dept

  18. Nov 27, 2018

    Passed: Building - Final

    Rec'd Bdt

    Inspected by Troy Crews

  19. Nov 27, 2018

    Failed: Building - Final

    Need Blower Door Test