Permit Details

Permit Search

Permit

New Residential Construction

11582 SW TUSTENUGGEE AVENUE FT.WHITE FL 32038

Permit #
000036617
Application #
37546
Status Completed
  1. Submitted Apr 23, 2018
  2. Issued Apr 23, 2018
  3. Expires May 29, 2019
  4. Completed Dec 3, 2018

Property

Parcel #
09621-113
Owner
Louis & Sheryl Ferrante
Acres
5.00
Subdivision
Tustenuggee Ridge
Zoning
AG-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0485C
This is the construction of a
SFD, UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
1923.00
Total Area (Sqft)
3030.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0293

Status & Review History

No status updates yet.

Contractors

  • Rodney Wade

    License
    CRC1331070
    Title
    —
    Role
    —

    County License & State License & Workers Comp Expired.

Inspections

  1. Apr 24, 2018

    Septic Release Inspection

    Inspected by Health Dept

  2. May 23, 2018

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  3. Jun 6, 2018

    Passed: Building - Slab

    Inspected by Troy Crews

  4. Jun 22, 2018

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  5. Jun 22, 2018

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  6. Jun 26, 2018

    Failed: Building - Framing

    Not Complete Anchor Bolts Strapping Etc.

    Inspected by Troy Crews

  7. Jul 2, 2018

    Passed: Building - Framing

    Items Corrected

    Inspected by Troy Crews

  8. Jul 13, 2018

    Rescheduled 7/16/2018:Electrical - Rough In

    Inspected by Laurie Hodson

  9. Jul 13, 2018

    Rescheduled 7/16/2018:Mechanical - Rough In

    Inspected by Laurie Hodson

  10. Jul 13, 2018

    Rescheduled 7/16/2018:Plumbing/Gas - Rough In

    Inspected by Laurie Hodson

  11. Jul 16, 2018

    Rescheduled 7/17/2018:Electrical - Rough In

    Inspected by Laurie Hodson

  12. Jul 16, 2018

    Rescheduled 7/17/2018:Mechanical - Rough In

    Inspected by Laurie Hodson

  13. Jul 16, 2018

    Rescheduled 7/17/2018:Plumbing/Gas - Rough In

    Inspected by Laurie Hodson

  14. Jul 17, 2018

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  15. Jul 17, 2018

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  16. Jul 17, 2018

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  17. Jul 25, 2018

    Passed: Building - Insulation

    Inspected by Randy Jones

  18. Oct 15, 2018

    Failed: Electrical - Permanent Power

    Ground Not Connected In Meter Can, Also Garage Needs To Be Lockable

    Inspected by Troy Crews

  19. Oct 16, 2018

    Rescheduled 10/18/2018:Building - Final

    Inspected by Troy Crews

  20. Oct 18, 2018

    Passed: Building - Final

    Inspected by Troy Crews

  21. Oct 18, 2018

    Release to power company

    Inspected by Troy Crews

  22. Oct 18, 2018

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  23. Oct 18, 2018

    Release to power company

    Inspected by Troy Crews

  24. Nov 30, 2018

    Passed: Building - Final

    Inspected by Troy Crews