Permit Details

Permit Search

Permit

New Residential Construction

140 SW LOTUS DR LAKE CITY FL 32024

Permit #
000036414
Application #
36985
Status Completed
  1. Submitted Mar 7, 2018
  2. Issued Mar 7, 2018
  3. Expires Feb 17, 2019
  4. Completed Sep 11, 2018

Property

Parcel #
02731-018
Owner
Preserve At Laurel Lake
Acres
0.36
Subdivision
Preserve @ Laurel Lk
Zoning
PRD
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0290D
This is the construction of a
SFD, UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
2
Heated Area (Sqft)
2681.00
Total Area (Sqft)
3639.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
X CITY

Status & Review History

No status updates yet.

Contractors

  • Aaron Simque

    License
    R282811879
    Title
    —
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Mar 14, 2018

    Passed: Engineering - Final Driveway

    Inspected by David Mccormick

  2. Mar 16, 2018

    Passed: Building - Footer

    Inspected by Troy Crews

  3. Mar 16, 2018

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  4. Mar 29, 2018

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  5. Apr 2, 2018

    Passed: Building - Slab

    Inspected by Troy Crews

  6. May 3, 2018

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  7. May 3, 2018

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  8. May 15, 2018

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  9. May 15, 2018

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  10. May 15, 2018

    Failed: Plumbing/Gas - Rough In

    Need Pressure On Lines

    Inspected by Troy Crews

  11. May 18, 2018

    Passed: Building - Framing

    Inspected by Troy Crews

  12. May 23, 2018

    Passed: Building - Insulation

    Inspected by Troy Crews

  13. Jul 19, 2018

    Failed: Electrical - Permanent Power

    Need Elevation Letter,

    Inspected by Troy Crews

  14. Aug 3, 2018

    Failed: Building - Final

    Permanent Power Inspection Not Complete Also Need Elevation Letter

    Inspected by Troy Crews

  15. Aug 21, 2018

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  16. Aug 21, 2018

    Release to power company

    Inspected by Troy Crews

  17. Aug 21, 2018

    Passed: Building - Final

    Need Engineer Letter, All Letters Rec'd 9/11/18

    Inspected by Troy Crews