Permit Details

Permit Search

Permit

New Residential Construction

388 SW BRECKENRIDGE LN FORT WHITE FL 32038

Permit #
000036225
Application #
36461
Status Completed
  1. Submitted Jan 22, 2018
  2. Issued Jan 22, 2018
  3. Expires Apr 27, 2019
  4. Completed Oct 30, 2018

Property

Parcel #
03789-003
Owner
John & Dianna Kebeck
Acres
38.00
Subdivision
—
Zoning
AG-3
Flood zone
X
District
2

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0480C
This is the construction of a
SFD, UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
2112.00
Total Area (Sqft)
2997.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
17-808

Status & Review History

No status updates yet.

Contractors

  • John Kebeck

    License
    OWNER
    Title
    —
    Role
    —

Inspections

  1. Jan 25, 2018

    Passed: Building - Footer

    Inspected by Troy Crews

  2. Jan 25, 2018

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. Feb 9, 2018

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  4. Feb 12, 2018

    Passed: Building - Slab

    Inspected by Troy Crews

  5. Apr 4, 2018

    Cancelled: Electrical - Temporary Service

    Per Owner, No Temp Pole Installed.

    Inspected by Laurie Hodson

  6. Apr 10, 2018

    Passed: Electrical - Temporary Service

    Inspected by Tommy Matthews

  7. Apr 11, 2018

    Release to power company

    Inspected by Tommy Matthews

  8. May 29, 2018

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Tommy Matthews

  9. May 29, 2018

    Passed: Building - Framing

    Inspected by Tommy Matthews

  10. Jun 6, 2018

    Passed: Electrical - Rough In

    Inspected by Tommy Matthews

  11. Jun 6, 2018

    Passed: Mechanical - Rough In

    Inspected by Tommy Matthews

  12. Jun 12, 2018

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  13. Jun 20, 2018

    Passed: Building - Insulation

    Inspected by Tommy Matthews

  14. Sep 6, 2018

    Passed: Electrical - Permanent Power

    Need Locks On Doors Prior To Power, Ok 9-10-18-tm

    Inspected by Tommy Matthews

  15. Sep 10, 2018

    Release to power company

    Inspected by Laurie Hodson

  16. Sep 10, 2018

    Septic Release Inspection

    Inspected by Health Dept

  17. Oct 29, 2018

    Passed: Building - Final

    Inspected by Troy Crews