Permit Details

Permit Search

Permit

New Residential Construction

509 NW CASTELWOOD COURT LAKE CITY FL 32055

Permit #
000036105
Application #
36301
Status Completed
  1. Submitted Dec 15, 2017
  2. Issued Dec 15, 2017
  3. Expires Mar 11, 2019
  4. Completed Sep 21, 2018

Property

Parcel #
01777-106
Owner
J. Dale & Mary Nanny
Acres
5.01
Subdivision
Suwannee Valley Farms
Zoning
A-3
Flood zone
X
District
1

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0186D
This is the construction of a
SFD/UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
2539.00
Total Area (Sqft)
4585.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
17-0733

Status & Review History

No status updates yet.

Contractors

  • Josh Sparks

    License
    CBC1252260
    Title
    —
    Role
    —

Inspections

  1. Dec 18, 2017

    Foundation Inspection

    Inspected by Troy Crews

  2. Dec 18, 2017

    Setback Inspection

    Inspected by Troy Crews

  3. Dec 18, 2017

    Passed: Building - Footer

    Inspected by Troy Crews

  4. Jan 10, 2018

    Passed: Plumbing/Gas - Underground Rough-In

    Waste Lines Only

    Inspected by Troy Crews

  5. Jan 12, 2018

    Passed: Building - Slab

    Inspected by Troy Crews

  6. Feb 6, 2018

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  7. Feb 6, 2018

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  8. Mar 7, 2018

    Failed: Building - Framing

    Garage Door Framing And Strapping

    Inspected by Troy Crews

  9. Mar 7, 2018

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  10. Mar 7, 2018

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  11. Mar 7, 2018

    Failed: Plumbing/Gas - Rough In

    Need Pressure

    Inspected by Troy Crews

  12. Mar 9, 2018

    Passed: Building - Framing

    Items Corrected

    Inspected by Troy Crews

  13. Mar 9, 2018

    Passed: Plumbing/Gas - Rough In

    100 Psi On Lies

    Inspected by Troy Crews

  14. Mar 16, 2018

    Passed: Building - Insulation

    Inspected by Troy Crews

  15. Jun 14, 2018

    Failed: Electrical - Permanent Power

    Need Door Locks

    Inspected by Troy Crews

  16. Jun 19, 2018

    Passed: Electrical - Permanent Power

    Pending Health Release(rec'd 6-29-18), Need Elevation Letter

    Inspected by Troy Crews

  17. Jun 29, 2018

    Septic Release Inspection

    Inspected by Health Dept

  18. Jul 2, 2018

    Release to power company

    Floor Height Letter Rec'd

    Inspected by Laurie Hodson

  19. Sep 12, 2018

    Passed: Building - Final

    Inspected by Troy Crews