Permit Details

Permit Search

Permit

New Residential Construction

448 SW ROSEMARY DR LAKE CITY FL 32024

Permit #
000035835
Application #
35847
Status Completed
  1. Submitted Oct 2, 2017
  2. Issued Oct 2, 2017
  3. Expires Mar 13, 2019
  4. Completed Sep 17, 2018

Property

Parcel #
02731-005
Owner
Preserve At Laurel Lake Inc
Acres
0.25
Subdivision
Preserve At Laurel Lake
Zoning
PRD
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0290D
This is the construction of a
SFD, UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
2471.00
Total Area (Sqft)
3382.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
X CITY

Status & Review History

No status updates yet.

Contractors

  • Aaron Simque

    License
    R282811879
    Title
    —
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Oct 25, 2017

    Foundation Inspection

    Inspected by Tommy Matthews

  2. Oct 25, 2017

    Setback Inspection

    Inspected by Tommy Matthews

  3. Nov 17, 2017

    Underslab Rough Plumbing Inspection

    Inspected by Troy Crews

  4. Dec 12, 2017

    Slab Inspection

    Inspected by Troy Crews

  5. Dec 12, 2017

    Passed: Building - Slab

    Inspected by Troy Crews

  6. Jan 17, 2018

    Passed: Building - Roof-In Progress

    Inspected by Troy Crews

  7. Jan 17, 2018

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  8. Jan 17, 2018

    Passed: Building - Framing

    Inspected by Troy Crews

  9. Jan 17, 2018

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  10. Jan 17, 2018

    Cancelled: Mechanical - Rough In

    Inspected by Troy Crews

  11. Jan 17, 2018

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  12. Jan 23, 2018

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  13. Jan 25, 2018

    Passed: Building - Insulation

    Inspected by Troy Crews

  14. Apr 19, 2018

    Release to power company

    Inspected by Troy Crews

  15. Apr 20, 2018

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  16. Sep 13, 2018

    Failed: Building - Final

    Need Blower Door Test. some Outlets Not Accessible In Garage. ac Room Not Accessible.

    Inspected by Tommy Matthews

  17. Sep 14, 2018

    Passed: Building - Final

    Inspected by Troy Crews