Permit Details

Permit Search

Permit

New Residential Construction

320 SW GRANITE COURT LAKE CITY FL 32024

Permit #
000035434
Application #
26357
Status Completed
  1. Submitted Jun 13, 2017
  2. Issued Jun 13, 2017
  3. Expires Jun 2, 2018
  4. Completed Dec 13, 2017

Property

Parcel #
03081-212
Owner
Mf Butler Homes, Llc
Acres
0.83
Subdivision
Wingate Estates
Zoning
PRD
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0380C
This is the construction of a
SFD/UTILITY
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
30.00
Stories
1
Heated Area (Sqft)
1871.00
Total Area (Sqft)
2557.00
Building Code Edition
Florida Building Code 2014 5th Edition & 2011 National Electrical Code
Septic# (00-0000) or (X00-000)
17-0340-N

Status & Review History

No status updates yet.

Contractors

  • Mark Bauer

    Gibraltar Contracting Llc

    License
    CBC1259633
    Title
    Cert Building
    Role
    —

    County License & State License Expired.

Inspections

  1. Jun 19, 2017

    Temporary Power Inspection

    Inspected by Troy Crews

  2. Jun 19, 2017

    Foundation Inspection

    Inspected by Troy Crews

  3. Jun 19, 2017

    Setback Inspection

    Inspected by Troy Crews

  4. Jun 30, 2017

    Underslab Rough Plumbing Inspection

    Inspected by Troy Crews

  5. Jul 5, 2017

    Slab Inspection

    Inspected by Troy Crews

  6. Aug 14, 2017

    Sheathing and Nailing Inspection

    Inspected by Troy Crews

  7. Aug 29, 2017

    Framing Inspection

    Inspected by Tommy Matthews

  8. Aug 29, 2017

    Rough-In Plumbing Inspection

    Inspected by Tommy Matthews

  9. Aug 29, 2017

    Electrical Rough-In Inspection

    Inspected by Tommy Matthews

  10. Aug 29, 2017

    Heat and Air Duct Inspection

    Inspected by Tommy Matthews

  11. Sep 5, 2017

    Insulation Inspection

    Inspected by Troy Crews

  12. Oct 31, 2017

    Permanent Power Inspection

    Inspected by Tommy Matthews

  13. Dec 4, 2017

    Passed: Building - Final

    Inspected by Troy Crews

  14. Dec 13, 2017

    Final Inspection

  15. Dec 13, 2017

    CERTIFICATE OF OCCUPANCY/COMPLETION DATE

  16. Dec 13, 2017

    Final Inspection

    Inspected by Troy Crews

  17. Requested

    Foundation

    Awaiting inspection

  18. Requested

    Temp Power

    Awaiting inspection

  19. Requested

    Under Slab Rough-in

    Awaiting inspection

  20. Requested

    Slab

    Awaiting inspection

  21. Requested

    Sheathing/Nailing

    Awaiting inspection

  22. Requested

    Sheathing/Nailing

    Awaiting inspection

  23. Requested

    Sheathing/Nailing

    Awaiting inspection

  24. Requested

    Above slab Rough-in

    Awaiting inspection

  25. Requested

    Electrical Rough-in

    Awaiting inspection

  26. Requested

    Framing

    Awaiting inspection

  27. Requested

    Heat & AC -

    Awaiting inspection

  28. Requested

    Temp Power - Above ground

    Awaiting inspection

  29. Requested

    Slab - Partial

    Awaiting inspection

  30. Requested

    Insulation

    Awaiting inspection