Permit Details

Permit Search

Permit

New Residential Construction

269 SW BUTTERCUP DR LAKE CITY FL 32024

Permit #
000034972
Application #
20944
Status Completed
  1. Submitted Feb 23, 2017
  2. Issued Feb 23, 2017
  3. Expires Aug 22, 2017
  4. Completed Jun 20, 2017

Property

Parcel #
03023-544
Owner
Millenia Capital, Inc.
Acres
0.59
Subdivision
Rolling Meadows
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0289D
This is the construction of a
SFD/UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
1763.00
Total Area (Sqft)
2470.00
Building Code Edition
Florida Building Code 2014 5th Edition & 2011 National Electrical Code
Septic# (00-0000) or (X00-000)
17-0090-N

Status & Review History

No status updates yet.

Contractors

  • Mark Bauer

    Gibraltar Contracting Llc

    License
    CBC1259633
    Title
    Cert Building
    Role
    —

    County License & State License Expired.

Inspections

  1. Feb 28, 2017

    Foundation Inspection

    Inspected by Troy Crews

  2. Feb 28, 2017

    Setback Inspection

    Inspected by Troy Crews

  3. Mar 14, 2017

    Slab Inspection

    Inspected by Troy Crews

  4. Mar 15, 2017

    Temporary Power Inspection

    Inspected by Troy Crews

  5. Mar 31, 2017

    Sheathing and Nailing Inspection

    Inspected by Troy Crews

  6. Apr 17, 2017

    Framing Inspection

    Inspected by Troy Crews

  7. Apr 17, 2017

    Rough-In Plumbing Inspection

    Inspected by Troy Crews

  8. Apr 17, 2017

    Electrical Rough-In Inspection

    Inspected by Troy Crews

  9. Apr 17, 2017

    Heat and Air Duct Inspection

    Inspected by Troy Crews

  10. Apr 18, 2017

    Insulation Inspection

    Inspected by Randy Jones

  11. Apr 18, 2017

    Insulation Inspection

    Inspected by Randy Jones

  12. Jun 1, 2017

    Permanent Power Inspection

    Inspected by Tommy Matthews

  13. Jun 20, 2017

    Final Inspection

    Inspected by Troy Crews

  14. Jun 20, 2017

    CERTIFICATE OF OCCUPANCY/COMPLETION DATE

  15. Requested

    Foundation

    Awaiting inspection

  16. Requested

    Temp Power

    Awaiting inspection

  17. Requested

    Under Slab Rough-in

    Awaiting inspection

  18. Requested

    Slab

    Awaiting inspection

  19. Requested

    Slab

    Awaiting inspection

  20. Requested

    Sheathing/Nailing - Roof & Wall

    Awaiting inspection

  21. Requested

    Above slab Rough-in

    Awaiting inspection

  22. Requested

    Electrical Rough-in

    Awaiting inspection

  23. Requested

    Framing

    Awaiting inspection

  24. Requested

    Heat & AC

    Awaiting inspection

  25. Requested

    Above slab Rough-in

    Awaiting inspection

  26. Requested

    Electrical Rough-in

    Awaiting inspection

  27. Requested

    Framing

    Awaiting inspection

  28. Requested

    Heat & AC

    Awaiting inspection

  29. Requested

    Insulation

    Awaiting inspection

  30. Requested

    Insulation

    Awaiting inspection

  31. Requested

    Final

    Awaiting inspection