Permit Details

Permit Search

Permit

New Residential Construction

190 SW CAMPHOR CT
LAKE CITY, FL 32024

Permit #
000034760
Application #
25481
Status Completed
  1. Submitted Dec 19, 2016
  2. Issued Apr 22, 2022
  3. Expires Oct 30, 2022
  4. Completed May 3, 2022

Property

Parcel #
02732-305
Owner
Harrington Land Trust Ii
Acres
0.50
Subdivision
Laurel Lake S/d
Zoning
PRD
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Document receieved
Yes
Fema map number
12023C0290D
This is the construction of a
SFD, UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
1922.00
Total Area (Sqft)
2012.00
Building Code Edition
Florida Building Code 2014 5th Edition & 2011 National Electrical Code
Septic# (00-0000) or (X00-000)
XCITY

Status & Review History

  1. Permit Renewed
  2. Permit reissued to reflect updated information.
  3. Permit Renewed
  4. Permit Renewed

Contractors

  • John Harrington Ii

    House Craft Homes,llc.

    License
    CGC1516998
    Title
    General Contractor
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Dec 22, 2016

    Setback Inspection

    Inspected by Troy Crews

  2. Dec 22, 2016

    Foundation Inspection

    Inspected by Troy Crews

  3. Jan 6, 2017

    Underslab Rough Plumbing Inspection

    Inspected by Troy Crews

  4. Jan 10, 2017

    Slab Inspection

    Inspected by Troy Crews

  5. Jan 20, 2017

    Perimeter Beam/Column Inspection

    Inspected by Tommy Matthews

  6. Feb 14, 2017

    Sheathing and Nailing Inspection

    Inspected by Troy Crews

  7. Jun 6, 2018

    Building-Framing

    Inspected by Troy Crews

  8. Jun 6, 2018

    Electrical -2nd Rough-In

    Inspected by Troy Crews

  9. Sep 20, 2018

    Building-Framing

    Inspected by Tommy Matthews

  10. Sep 20, 2018

    Electrical -2nd Rough-In

    Inspected by Tommy Matthews

  11. Sep 20, 2018

    Plumbing/Gas-2nd Rough-In

    Inspected by Tommy Matthews

  12. Oct 19, 2018

    Mechanical-Rough In

    Inspected by Troy Crews

  13. Nov 6, 2018

    Electrical -Temporary Service

    Released Power On 11-6-18

    Inspected by Tommy Matthews

  14. Sep 11, 2019

    Electrical -Permanent Power

    Need Culvert Final Inspection 2356-rec'd

    Inspected by Troy Crews

  15. Jul 7, 2020

    Release to power company

    Resent To Power Company

    Inspected by Laurie Hodson

  16. Apr 25, 2022

    Failed: Building - Final

    Sewer Cleanout Broken Off Needs Repair, Front Steps Need Handrail 4 Risers, Need Shutdown Switch On Air Handler Condensate Line, Need Blower Door Test.

    Inspected by Troy Crews

  17. May 3, 2022

    Passed: Building - Final

    Air Handler Shut Down Switch Inside Unit Per Contractor.

    Inspected by Troy Crews