Permit Details

Permit Search

Permit

New Residential Construction

217 SW NEWLYWED CT LAKE CITY FL 32024

Permit #
000034369
Application #
25475
Status Completed
  1. Submitted Sep 23, 2016
  2. Issued Sep 23, 2016
  3. Expires Mar 22, 2017
  4. Completed Feb 2, 2017

Property

Parcel #
02973-118
Owner
Bullard Management Services Inc
Acres
0.05
Subdivision
Hintington Place
Zoning
RSF-2
Flood zone
X SP
District
3

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0293D
This is the construction of a
SFD, UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
1780.00
Total Area (Sqft)
2464.00
Building Code Edition
Florida Building Code 2014 5th Edition & 2011 National Electrical Code
Septic# (00-0000) or (X00-000)
16-0489

Status & Review History

No status updates yet.

Contractors

  • Adam Papka

    Adam's Construction Llc

    License
    CBC1253409
    Title
    Building Contractor
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Aug 29, 2016

    Foundation Inspection

    Inspected by Troy Crews

  2. Aug 29, 2016

    Setback Inspection

    Inspected by Troy Crews

  3. Sep 7, 2016

    Underslab Rough Plumbing Inspection

    Inspected by Troy Crews

  4. Sep 12, 2016

    Slab Inspection

    Inspected by Troy Crews

  5. Sep 27, 2016

    Sheeting and Nailing Inspection

    Inspected by Tommy Matthews

  6. Sep 27, 2016

    Sheathing and Nailing Inspection

    Inspected by Tommy Matthews

  7. Sep 28, 2016

    Temporary Power Inspection

    Inspected by Randy Jones

  8. Sep 28, 2016

    Temporary Power Inspection

    Inspected by Randy Jones

  9. Sep 30, 2016

    Framing Inspection

    Inspected by Troy Crews

  10. Oct 11, 2016

    Rough-In Plumbing Inspection

    Inspected by Troy Crews

  11. Oct 11, 2016

    Electrical Rough-In Inspection

    Inspected by Troy Crews

  12. Oct 11, 2016

    Heat and Air Duct Inspection

    Inspected by Troy Crews

  13. Oct 17, 2016

    Insulation Inspection

    Inspected by Troy Crews

  14. Nov 21, 2016

    CERTIFICATE OF OCCUPANCY/COMPLETION DATE

  15. Nov 28, 2016

    Permanent Power Inspection

    Inspected by Troy Crews

  16. Feb 2, 2017

    Final Inspection

  17. Feb 2, 2017

    Final Inspection

    Inspected by Troy Crews

  18. Feb 3, 2017

    CERTIFICATE OF OCCUPANCY/COMPLETION DATE

  19. Requested

    Foundation

    Awaiting inspection