Permit Details

Permit Search

Permit

New Commercial Construction

1550 SW BEDENBAUGH LN LAKE CITY FL 32025

Permit #
000034059
Application #
32999
Status Completed
  1. Submitted May 13, 2016
  2. Issued May 13, 2016
  3. Expires Nov 9, 2016
  4. Completed Sep 22, 2016

Property

Parcel #
08916-000
Owner
Gateway Development,llc.
Acres
42.00
Subdivision
—
Zoning
AG-3
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0382D
This is the construction of a:
OFFICE/WAREHOUSE
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setback Rear
25.00
Stories
1
Total Area (Sqft)
3840.00
Building Code Edition
Florida Building Code 2014 5th Edition & 2011 National Electrical Code
Septic# (00-0000) or (X00-000)
16-0296

Status & Review History

No status updates yet.

Contractors

  • David Simque

    Simque Construction, Llc

    License
    CGC1516165
    Title
    General Contractor
    Role
    —

    County License & State License & Liability Insurance Expired.

Inspections

  1. May 16, 2016

    Temporary Power Inspection

    Inspected by Troy Crews

  2. Jun 2, 2016

    Underslab Rough Plumbing Inspection

    Inspected by Randy Jones

  3. Jun 2, 2016

    Underslab Rough Plumbing Inspection

    Inspected by Randy Jones

  4. Jun 13, 2016

    Monolithic Slab Inspection

    Inspected by Troy Crews

  5. Jun 13, 2016

    Setback Inspection

    Inspected by Troy Crews

  6. Jul 21, 2016

    Framing Inspection

    Inspected by Randy Jones

  7. Jul 21, 2016

    Rough-In Plumbing Inspection

    Inspected by Randy Jones

  8. Jul 21, 2016

    Electrical Rough-In Inspection

    Inspected by Randy Jones

  9. Jul 21, 2016

    Heat and Air Duct Inspection

    Inspected by Randy Jones

  10. Jul 21, 2016

    Insulation Inspection

    Inspected by Randy Jones

  11. Jul 21, 2016

    Framing Inspection

    Inspected by Randy Jones

  12. Jul 21, 2016

    Rough-In Plumbing Inspection

    Inspected by Randy Jones

  13. Jul 21, 2016

    Electrical Rough-In Inspection

    Inspected by Randy Jones

  14. Jul 21, 2016

    Heat and Air Duct Inspection

    Inspected by Randy Jones

  15. Jul 21, 2016

    Insulation Inspection

    Inspected by Randy Jones

  16. Aug 11, 2016

    Permanent Power Inspection

    Inspected by Randy Jones

  17. Aug 11, 2016

    Permanent Power Inspection

    Inspected by Randy Jones

  18. Sep 22, 2016

    Final Inspection

    Inspected by Troy Crews

  19. Sep 23, 2016

    CERTIFICATE OF OCCUPANCY/COMPLETION DATE

  20. Requested

    Slab

    Awaiting inspection