Permit Details

Permit Search

Permit

New Residential Construction

247 SW CAMPHOR CT LAKE CITY FL 32024

Permit #
000032576
Application #
25404
Status Completed
  1. Submitted Dec 30, 2014
  2. Issued Dec 30, 2014
  3. Expires Jun 28, 2015
  4. Completed Jun 22, 2016

Property

Parcel #
02732-310
Owner
Blake Graham
Acres
0.67
Subdivision
Laurel Lake S/d (between 9 & 10)
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0290D
This is the construction of a
SFD, UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
2100.00
Total Area (Sqft)
2800.00
Building Code Edition
Florida Building Code 2014 5th Edition & 2011 National Electrical Code

Status & Review History

No status updates yet.

Contractors

This is an owner-builder project.

  • Blake Graham

    License
    OWNER
    Title
    —
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Jun 9, 2015

    Temporary Power Inspection

    Inspected by Troy Crews

  2. Oct 5, 2015

    Setback Inspection

    Inspected by Troy Crews

  3. Oct 8, 2015

    Foundation Inspection

    Inspected by Troy Crews

  4. Dec 11, 2015

    Slab Inspection

    Inspected by Troy Crews

  5. Jan 12, 2016

    Underslab Rough Plumbing Inspection

    Inspected by Troy Crews

  6. Jan 12, 2016

    Sheathing and Nailing Inspection

    Inspected by Troy Crews

  7. Feb 16, 2016

    Rough-In Plumbing Inspection

    Inspected by Troy Crews

  8. Feb 16, 2016

    Electrical Rough-In Inspection

    Inspected by Troy Crews

  9. Feb 16, 2016

    Heat and Air Duct Inspection

    Inspected by Troy Crews

  10. Feb 18, 2016

    Framing Inspection

    Inspected by Troy Crews

  11. Feb 24, 2016

    Insulation Inspection

    Inspected by Troy Crews

  12. Apr 29, 2016

    Permanent Power Inspection

    Inspected by Troy Crews

  13. Jun 22, 2016

    Final Inspection

  14. Jun 23, 2016

    CERTIFICATE OF OCCUPANCY/COMPLETION DATE