Permit Details

Permit Search

Permit

New Residential Construction

122 SW ARROW GLEN LAKE CITY FL 32024

Permit #
000032540
Application #
25399
Status Completed
  1. Submitted Dec 15, 2014
  2. Issued Dec 15, 2014
  3. Expires Jun 13, 2015
  4. Completed Sep 28, 2015

Property

Parcel #
03114-114
Owner
Conner Investmets Of Florida Inc
Acres
0.51
Subdivision
Cannon Creek Place
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0293D
This is the construction of a
SFD, UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
1658.00
Total Area (Sqft)
2424.00
Building Code Edition
Florida Building Code 2014 5th Edition & 2011 National Electrical Code

Status & Review History

No status updates yet.

Contractors

  • James Johnson

    Hometown Homes,llc

    License
    CRC1328128
    Title
    Residential Contractor
    Role
    —

    County License & State License & Liability Insurance & Workers Comp & Employees Workers Comp Expired.

Inspections

  1. Dec 18, 2014

    Foundation Inspection

    Inspected by Troy Crews

  2. Dec 18, 2014

    Setback Inspection

    Inspected by Troy Crews

  3. Dec 29, 2014

    Underslab Rough Plumbing Inspection

    Inspected by Troy Crews

  4. Dec 31, 2014

    Temporary Power Inspection

    Inspected by Troy Crews

  5. Dec 31, 2014

    Slab Inspection

    Inspected by Troy Crews

  6. Jan 27, 2015

    Sheeting and Nailing Inspection

    Inspected by Troy Crews

  7. Jan 27, 2015

    Sheathing and Nailing Inspection

    Inspected by Troy Crews

  8. Feb 10, 2015

    Rough-In Plumbing Inspection

    Inspected by Troy Crews

  9. Feb 10, 2015

    Heat and Air Duct Inspection

    Inspected by Troy Crews

  10. Feb 12, 2015

    Framing Inspection

    Inspected by Tommy Matthews

  11. Feb 12, 2015

    Electrical Rough-In Inspection

    Inspected by Tommy Matthews

  12. Feb 12, 2015

    Insulation Inspection

    Inspected by Tommy Matthews

  13. Jul 6, 2015

    Permanent Power Inspection

    Inspected by Troy Crews

  14. Sep 28, 2015

    Final Inspection