Permit Details

Permit Search

Permit

Swimming Pool and Spa

223 SW ZINNIA GLN
FORT WHITE, FL 32038

Permit #
000056705
Application #
78808
Status Permit Issued
  1. Submitted Sep 9, 2026
  2. Issued Oct 1, 2026
  3. Expires May 5, 2027
  4. Completed —

Property

Parcel #
09696-129
Owner
Mckenzie Terry, Booth Nicole Shanna
Acres
10.02
Subdivision
Tustenuggee Plantation Unit 2 Unr
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Permit Issued
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Accessory Use
Finished floor requirement
Non-Habitable Structure
Fema map number
12023C0485C
Is this for residential or commercial use?
Residential
This is the construction of a:
Pool
ADA Compliant
No
Setbacks Front
30'
Setback Side 1
25'
Setbacks Rear
25'
Setback Side 2
25'
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
26-0662
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application Status Update Notification
  3. Application Status Update Notification
  4. Septic Approval Paperwork was not accepted.
  5. Submitted by building department on applicant's behalf
  6. Application Status Update Notification
  7. Application Status Update Notification
  8. Application Status Update Notification
  9. Application Status Update Notification
  10. Application Status Update Notification
  11. Application Status Update Notification
  12. Application Status Update Notification
  13. Application Status Update Notification
  14. Application Status Update Notification
  15. Application Status Update Notification
  16. Permit Issued

Contractors

  • Brent D Handy

    Paragon Pools Of North Florida Llc

    License
    CPC1456799
    Title
    Residential Pool/spa Contractor
    Role
    Contractor
  • Nick Q Thornton

    Precision Power Works

    License
    EC13014542
    Title
    Cert. Electrical
    Role
    Subcontractor
  1. Sep 9, 2026

    Septic Release Inspection

    Inspected by Health Dept

  2. Nov 6, 2026

    Passed: Engineering - Setbacks

    Appears To Be With Plan, No Markers Visiable

    Inspected by Gary Pitzer

  3. Nov 6, 2026

    Passed: Swimming Pool - Pool Footer

    Inspected by Gary Pitzer

  4. Nov 6, 2026

    Passed: Swimming Pool - Pool Deck/Piping Pressure

    Pressure On System, Photo On File

    Inspected by Gary Pitzer

  5. Nov 6, 2026

    Passed: Electrical - Pool/Deck Bonding

    Underground Conduits Installed, All Steel Wired And Bonded

    Inspected by Gary Pitzer

  6. Nov 6, 2026

    Passed: Swimming Pool - Pool Steel and Ground

    All Piping Covered, Pressure On System Bonding Complete With Long Tail To Future Equipment. Ok To Proceed

    Inspected by Gary Pitzer