Permit Details

Permit Search

Permit

Storage Building

9830 SW TUSTENUGGEE AVE
LAKE CITY, FL 32024

Permit #
000056403
Application #
76140
Status Permit Reissued
  1. Submitted Aug 20, 2026
  2. Issued Oct 5, 2026
  3. Expires Apr 12, 2027
  4. Completed —

Property

Parcel #
09613-003
Owner
Carter Shane And Alicia Revocable Trust Agreement Dated January 30, 2026,
Acres
12.99
Subdivision
—
Zoning
A-3
Flood zone
A
District
4

Permit

Status
Permit Reissued
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Accessory Use
Finished floor requirement
Non-Habitable Structure
Fema map number
12023C0395C
Type of Structure
Storage Building
Commercial or Residential?
Residential
Total Area (Sqft)
1600
Septic# (00-0000) or (X00-000)
X26-110
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setback Rear
10' (ACCESSORY)
Building Code Construction Type
III
Building Code Element
B
Building Code Occupancy Types
Storage
Occupancy Use Title
NON-HABITABLE STRUCTURE
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Building Height
14'
Building Length
40'
Building Width
40'
Service Amps
100
Slab
New
Mechanical
No
Electrical
Yes
Plumbing
No

Status & Review History

  1. Application pending.
  2. Corporate Articles Listing the Owner or POA Form or Executor Documents was not accepted.
  3. Corporate Articles Listing the Owner or POA Form or Executor Documents was not accepted.
  4. Metal Building Plans was not accepted.
  5. Subcontractor Form was not accepted.
  6. Structural Engineering and Wind Load Calculations was not accepted.
  7. Application Status Update Notification
  8. Application Status Update Notification
  9. Application Status Update Notification
  10. Application Status Update Notification
  11. Application Status Update Notification
  12. Application Status Update Notification
  13. Application Status Update Notification
  14. Application Status Update Notification
  15. Application Status Update Notification
  16. Application Status Update Notification
  17. Application Status Update Notification
  18. Application Status Update Notification
  19. Application Status Update Notification
  20. Application Status Update Notification
  21. Application Status Update Notification
  22. Application Status Update Notification
  23. Application Status Update Notification
  24. Application Status Update Notification
  25. Application Status Update Notification
  26. Application Status Update Notification
  27. Application Status Update Notification
  28. Application Status Update Notification
  29. Application Status Update Notification
  30. Application Status Update Notification
  31. Recorded Notice of Commencement was not accepted.
  32. Application Status Update Notification
  33. Application Status Update Notification
  34. Application Status Update Notification
  35. Submitted by building department on applicant's behalf
  36. Application Status Update Notification
  37. Application Status Update Notification
  38. Permit Issued
  39. Permit Renewed
  40. Permit Reissued

Contractors

This is an owner-builder project.

  1. Aug 19, 2026

    Septic Release Inspection

    Inspected by Health Dept

  2. Oct 14, 2026

    Passed: Building - Monolithic Slab

    Approved Mono Slab No Plumbing Or Electrical

    Inspected by Troy Crews

  3. Oct 14, 2026

    Passed: Engineering - Setbacks

    Approved