| 3/17/2026 |
Email confirmation reminder sent. |
| 3/18/2026 |
Pending applicant completion and submission. |
| 3/18/2026 |
Application Status Update Notification |
| 3/27/2026 |
Application Status Update Notification |
| 3/30/2026 |
Application Status Update Notification |
| 3/31/2026 |
Email confirmation reminder sent. |
| 4/14/2026 |
Email confirmation reminder sent. |
| 4/14/2026 |
Application Status Update Notification |
| 4/28/2026 |
Email confirmation reminder sent. |
| 4/28/2026 |
Application submitted by applicant. |
| 4/28/2026 |
Pending Public Works Application Approval |
| 4/28/2026 |
Application Approved by Public Works |
| 4/28/2026 |
Application submitted by applicant. |
| 4/28/2026 |
Pending Public Works Application Approval |
| 4/29/2026 |
Permit Issued |