Permit Details

Permit Search

Permit

Remodel

149 SW WOOLSEY GLN
LAKE CITY, FL 32024

Permit #
000055199
Application #
75179
Status Completed
  1. Submitted Feb 16, 2026
  2. Issued Mar 10, 2026
  3. Expires Dec 15, 2026
  4. Completed Jun 18, 2026

Property

Parcel #
02719-000
Owner
Woods Project Llc,
Acres
7.11
Subdivision
—
Zoning
CI
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0291D
Type of Structure
Other
Commercial or Residential?
Commercial
Description of the work being performed:
Interior buildout
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Service Amps
220

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. City of Lake City Utilities Notified.
  4. Application Status Update Notification
  5. Application submitted by applicant.
  6. Application Status Update Notification
  7. Application Status Update Notification
  8. Application Status Update Notification
  9. Application Status Update Notification
  10. Application Status Update Notification
  11. Application Status Update Notification
  12. Application Status Update Notification
  13. Application Status Update Notification
  14. Permit Issued

Contractors

  • Benjamin L Sparks

    Line Electric Company Llc

    License
    EC13009101
    Title
    Cert. Electrical
    Role
    Subcontractor

    County License & State License Expired.

  • Clinton G Wilson

    Wilson Heat & Air Inc

    License
    CAC057886
    Title
    Class B A/c
    Role
    Subcontractor
  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Josh Sparks

    Sparks Construction

    License
    CBC1252260
    Title
    Building Contractor
    Role
    Contractor

Inspections

  1. Mar 3, 2026

    Passed: Fire - Plan Review

    Inspected by Cpt. Shane Overstreet

  2. Apr 6, 2026

    Rescheduled 4/8/2026:Electrical - 2nd Rough-In

    Inspected by Tcrews

  3. Apr 8, 2026

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  4. Apr 16, 2026

    Passed: Building - Insulation

    Spray Foam Metal Shell

    Inspected by Troy Crews

  5. Jun 9, 2026

    Failed: Building - Final

    Need To Cover All Electrical Boxes, Wall Plates, Fire Extinguishers At Both Doors Occupant Load Posted Both Doors Per Permit, Plumbing Not Complete.

    Inspected by Troy Crews

  6. Jun 9, 2026

    Failed: Fire - Fire Final

    Inspected by Cpt. S Overstreet

  7. Jun 17, 2026

    Failed: Fire - Fire Final

    Occupancy Signs Need To Be Permanently Mounted Also Plumbing Still Sticking Up Causing A Trip Hazard

    Inspected by Troy Crews

  8. Jun 17, 2026

    Failed: Building - Final

    Occupancy Signs Need To Be Permanently Mounted Plumbing Still Sticking Up Causing Trip Hazard

    Inspected by Troy Crews

  9. Jun 18, 2026

    Passed: Building - Final

    Occupant Load Posted And Plumbing Capped Off

    Inspected by Troy Crews