| 7/8/2025 |
Application pending. |
| 7/10/2025 |
Point Review - Pre-submittal Review Notes |
| 7/11/2025 |
Application submitted by applicant. |
| 7/15/2025 |
Point Review - Pre-submittal Review Notes |
| 7/15/2025 |
Point Review - Pre-submittal Review Notes |
| 7/15/2025 |
Point Review - Pre-submittal Review Notes |
| 7/15/2025 |
Point Review - Pre-submittal Review Notes |
| 7/30/2025 |
Point Review - Ready for applicant submittal |
| 7/30/2025 |
Point Review - Reviewed |
| 7/30/2025 |
Zoning Review - Reviewed |
| 7/31/2025 |
Plan Review - Documents Required |
| 8/1/2025 |
Plan Review - Documents Required |
| 8/4/2025 |
Plan Review - Documents Required |
| 8/13/2025 |
Plan Review - Documents Required |
| 8/26/2025 |
Plan Review - Documents Required |
| 8/27/2025 |
Plan Review - Documents Required |
| 9/1/2025 |
Plan Review - Documents Required |
| 9/5/2025 |
Plan Review - Documents Required |
| 9/9/2025 |
Plan Review - Documents Required |
| 9/10/2025 |
Plan Review - Documents Required |
| 9/11/2025 |
Plan Review - Documents Required |
| 9/14/2025 |
Plan Review - Documents Required |
| 9/16/2025 |
Plan Review - Documents Required |
| 9/21/2025 |
Plan Review - Documents Required |
| 9/25/2025 |
Plan Review - Documents Required |
| 9/28/2025 |
Plan Review - Documents Required |
| 10/6/2025 |
Plan Review - Sent to plan review |
| 10/9/2025 |
Plan Review - Reviewed |
| 10/9/2025 |
Final Review - Sent for final review |
| 10/28/2025 |
Final Review - Documents Required |
| 10/30/2025 |
Final Review - Reviewed |
| 10/30/2025 |
Final Review - Payment Needed |
| 11/3/2025 |
Permit Issued |