| Passed: Building - Footer |
Per Builder We Will Be Supplied With The House Placed On Wetland Delineation Tomorrow Am Showing The 35 Set Back Line |
Troy Crews |
11/3/2025 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
11/3/2025 |
| Passed: Building - Footer |
Wetlands Set Back Has Been Marked By Surveyor Picture In File |
Troy Crews |
11/24/2025 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
Waste Pipe With Hvac Chase Observed |
Matt Forsyth |
12/10/2025 |
| Passed: Building - Slab |
|
Matt Forsyth |
12/12/2025 |
| Failed: Building - Ext Strapping/Wall Sheathing |
1. Wall And Roof Sheathing Only, 2. Work Is Still In Progress On Framing And Strapping, 3. Few Small Areas Of Wall Sheathing In Progress |
Gary Pitzer |
1/2/2026 |
| Failed: Building - Framing |
Still In Progress |
Gary Pitzer |
1/2/2026 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
1/9/2026 |
| Passed: Building - Framing |
|
Matt Forsyth |
1/21/2026 |
| Passed: Building - Strapping |
|
Matt Forsyth |
1/21/2026 |
| Passed: Electrical - 1st Underground Rough–In |
|
Matt Forsyth |
1/21/2026 |
| Passed: Plumbing/Gas - 2nd Rough-In |
Upstairs Water Tested |
Matt Forsyth |
1/21/2026 |
| Failed: Mechanical - Rough In |
Not Complete |
Matt Forsyth |
1/21/2026 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
1/26/2026 |
| Passed: Building - Insulation |
|
Matt Forsyth |
2/6/2026 |
| Passed: Electrical - Permanent Power |
Septic Rec'd 6.24.26, Ok To Release Power-- Mg |
Matt Forsyth |
5/27/2026 |
| Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Matt Forsyth |
6/22/2026 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
6/22/2026 |
| Release to power company |
|
Mgarber |
6/24/2026 |
| Septic Release Inspection |
|
Health Dept |
6/24/2026 |
| Failed: Building - Final |
Stair Railing Not Complete |
Matt Forsyth |
9/15/2026 |