Permit Details

Permit Search

Permit

New Residential Construction

289 SW BEDENBAUGH LN
LAKE CITY, FL 32025

Permit #
000054213
Application #
73214
Status Completed
  1. Submitted Sep 11, 2025
  2. Issued Oct 8, 2025
  3. Expires Jun 21, 2026
  4. Completed Jan 2, 2026

Property

Parcel #
08835-009
Owner
Bedenbaugh Kevin L Jr, Bedenbaugh Amy E
Acres
12.60
Subdivision
—
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0401C
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
1152
Total Area (Sqft)
2844
Building Height
28
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
25-0673
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
a self-adhering polymer-modified bitumen underlayment complying with ASTM D1970 applied over the entire roof.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Point Review - Pre-submittal Review Notes
  3. Point Review - Processing
  4. Point Review - Pre-submittal Review Notes
  5. Point Review - Ready for applicant submittal
  6. Application submitted by applicant.
  7. Application submitted by applicant.
  8. Point Review - Processing
  9. Zoning Review - Sent for Zoning Review
  10. Zoning Review - Reviewed
  11. Plan Review - Sent to plan review
  12. Plan Review - Plumbing Approved
  13. Plan Review - Mechanical Approved
  14. Plan Review - Electrical Approved
  15. Plan Review - Building Approved
  16. Plan Review - Reviewed
  17. Final Review - Sent for final review
  18. Zoning Review - Reviewed
  19. Final Review - Processing
  20. Final Review - Reviewed
  21. Final Review - Payment Needed
  22. Final Review - Complete
  23. Permit Issued

Contractors

  • Kevin L Bedenbaugh Jr

    Plumb Level Construction Co Llc

    License
    CGC1516042
    Title
    General Contractor
    Role
    Contractor
  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Kevin L Bedenbaugh Jr

    Plumb Level Construction Co Llc

    License
    CCC1329482
    Title
    Roofing Contractor
    Role
    Subcontractor
  • Ryan Felknor

    Felknor Electric, Inc.

    License
    EC13003153
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Clinton G Wilson

    Wilson Heat & Air Inc

    License
    CAC057886
    Title
    Class B A/c
    Role
    Subcontractor

Inspections

  1. Oct 9, 2025

    Passed: Electrical - Temporary Power Service

    400 Amp Service To Service Existing Barn And To Be Used For New Construction A Final Will Be Called In At The End Of Construction

    Inspected by Troy Crews

  2. Oct 13, 2025

    Release to power company

    Temp Power For Existing And New Structure

    Inspected by Tcrews

  3. Oct 17, 2025

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Matt Forsyth

  4. Oct 21, 2025

    Passed: Building - Monolithic Slab

    Inspected by Matt Forsyth

  5. Oct 21, 2025

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  6. Nov 7, 2025

    Passed: Building - Roof Decking

    Inspected by Matt Forsyth

  7. Nov 7, 2025

    Passed: Building - Wall Sheathing

    Inspected by Matt Forsyth

  8. Nov 12, 2025

    Passed: Building - Framing

    Inspected by Matt Forsyth

  9. Nov 12, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Matt Forsyth

  10. Nov 12, 2025

    Passed: Electrical - 2nd Rough-In

    20 Amp Receptacle Added To Carport

    Inspected by Matt Forsyth

  11. Nov 12, 2025

    Passed: Mechanical - Rough In

    Inspected by Matt Forsyth

  12. Nov 14, 2025

    Passed: Building - Insulation

    Inspected by Matt Forsyth

  13. Dec 23, 2025

    Passed: Electrical - Permanent Power

    Inspected by Matt Forsyth

  14. Dec 23, 2025

    Release to power company

    Inspected by Matt Forsyth

  15. Dec 23, 2025

    Passed: Building - Final

    All Requirements Met To Release Co-- 1.2.26 Mg

    Inspected by Matt Forsyth

  16. Jan 12, 2026

    Septic Release Inspection

    Inspected by Health Dept

Documents