Permit Details

Permit Search

Permit

New Residential Construction

593 SW BELLFLOWER DR
LAKE CITY, FL 32024

Permit #
000054161
Application #
72759
Status Completed
  1. Submitted Aug 18, 2025
  2. Issued Sep 29, 2025
  3. Expires Jan 16, 2027
  4. Completed Jul 24, 2026

Property

Parcel #
02731-039
Owner
Adams Homes Of Northwest Florida, Inc,
Acres
0.26
Subdivision
Preserve At Laurel Lake Unit 1
Zoning
PRD
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
106.8'
Requirement needed
By Nailing Inspection
Document needed is
a Surveyor letter giving the Finished Floor Elevation
Document receieved
No
Fema map number
12023C0290D
This is the construction of a
Single Family Dwelling
Setbacks Front
25'
Setback Side 1
10'
Setback Side 2
10'
Setbacks Rear
15'
Stories
1
Heated Area (Sqft)
1816
Total Area (Sqft)
2397
Building Height
18
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
SINGLE FSMILY DWELLING
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
X-CITY
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps
200

Status & Review History

  1. Application pending.
  2. City of Lake City Utilities Notified.
  3. Point Review - Pre-submittal Review Notes
  4. Point Review - Pre-submittal Review Notes
  5. Point Review - Pre-submittal Review Notes
  6. Point Review - Pre-submittal Review Notes
  7. Point Review - Ready for applicant submittal
  8. Point Review - Ready for applicant submittal
  9. Application submitted by applicant.
  10. City of Lake City Utilities Notified.
  11. Point Review - Reviewed
  12. Zoning Review - Reviewed
  13. Plan Review - Sent to plan review
  14. Plan Review - Corrections Needed
  15. Plan Review - Sent to plan review
  16. Plan Review - Building Approved
  17. Plan Review - Electrical Approved
  18. Plan Review - Mechanical Approved
  19. Plan Review - Plumbing Approved
  20. Plan Review - Fuel/Gas Approved
  21. Plan Review - Reviewed
  22. Final Review - Sent for final review
  23. Final Review - Reviewed
  24. Final Review - Payment Needed
  25. Permit Issued

Contractors

  • William Adams

    Adams Homes Of Northwest Florida Inc

    License
    CRC1330146
    Title
    Cert. Residential
    Role
    Contractor
  • Joseph H Strada Jr

    Strada Services Inc Dba Strada Electric & Security

    License
    EC13003715
    Title
    Cert Electrical
    Role
    Subcontractor

    Liability Insurance & Workers Comp Expired.

  • Joseph H Strada Jr

    Strada Services Inc

    License
    CAC043953
    Title
    Cert. A/c Class “b”
    Role
    Subcontractor

    Liability Insurance & Workers Comp & Employees Workers Comp Expired.

  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Benjamin T Keeler

    Keeler Roofing, Llc

    License
    CCC1330509
    Title
    Cert. Roofing
    Role
    Subcontractor

Inspections

  1. Feb 4, 2026

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Troy Crews

  2. Feb 6, 2026

    Passed: Building - Monolithic Slab

    Inspected by Troy Crews

  3. Feb 6, 2026

    Passed: Electrical - Footer Steel & Grounding

    Inspected by Troy Crews

  4. Feb 6, 2026

    Passed: Engineering - Setbacks

    Setbacks To Be Confirmed By Surveyor

    Inspected by Troy Crews

  5. Mar 2, 2026

    Passed: Building - Wall Sheathing

    Inspected by Troy Crews

  6. Mar 2, 2026

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  7. Mar 6, 2026

    Passed: Building - Framing

    Check Anchor B On East And South Walls At Insulation

    Inspected by Troy Crews

  8. Mar 6, 2026

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  9. Mar 6, 2026

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  10. Mar 6, 2026

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  11. Mar 16, 2026

    Passed: Building - Insulation

    Inspected by Troy Crews

  12. May 7, 2026

    Passed: Electrical - Permanent Power

    Cannot Release Power Until Driveway Permit Has Final Inspection.

    Inspected by Troy Crews

  13. May 15, 2026

    Passed: City of Lake City Utilities - Lake City Utilities Tap Inspection

    Inspected by City Of Lake City Distribution And Collections Department

  14. May 20, 2026

    Release to power company

    Inspected by Tcrews

  15. May 20, 2026

    Submitted Power Release through FPL Portal

    Inspected by Ward, Emaleigh C.

  16. Jul 20, 2026

    Passed: Building - Final

    Contractor Working On Valley At Garage Small Leak - Troy Ok'd This 7.23.26 Mg

    Inspected by Troy Crews

Documents