| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
2/4/2026 |
| Rescheduled 2/9/2026:Building - Monolithic Slab |
|
Tcrews |
2/6/2026 |
| Rescheduled 2/9/2026:Electrical - Footer Steel & Grounding |
|
Tcrews |
2/6/2026 |
| Rescheduled 2/9/2026:Engineering - Setbacks |
|
Tcrews |
2/6/2026 |
| Passed: Building - Monolithic Slab |
|
Troy Crews |
2/9/2026 |
| Passed: Electrical - Footer Steel & Grounding |
Need Ground Wire Installed Prior To Pour |
Troy Crews |
2/9/2026 |
| Passed: Engineering - Setbacks |
Setbacks To Be Confirmed By Surveyor |
Troy Crews |
2/9/2026 |
| Passed: Building - Roof Decking |
|
Troy Crews |
2/18/2026 |
| Passed: Building - Wall Sheathing |
|
Troy Crews |
2/18/2026 |
| Cancelled: Building - Ext Strapping/Wall Sheathing |
Already Done |
Tcrews |
3/5/2026 |
| Failed: Building - Framing |
Windows Not Complete With All Screws |
Troy Crews |
3/5/2026 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
3/5/2026 |
| Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Troy Crews |
3/5/2026 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
3/5/2026 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
3/5/2026 |
| Passed: Building - Framing |
Window Screws Have Been Completed |
Troy Crews |
3/6/2026 |
| Passed: Building - Insulation |
Batts On Walls And Partial Ceiling |
Gary Pitzer |
3/11/2026 |
| Passed: Electrical - Permanent Power |
Cannot Release Power Until Driveway Permit Has Final Inspection. |
Troy Crews |
5/7/2026 |
| Passed: City of Lake City Utilities - Lake City Utilities Tap Inspection |
|
City Of Lake City Distribution And Collections Department |
5/15/2026 |
| Release to power company |
|
Tcrews |
5/20/2026 |
| Submitted Power Release through FPL Portal |
|
Ward, Emaleigh C. |
5/20/2026 |