| 5/30/2025 |
Application pending. |
| 6/4/2025 |
Point Review - Pre-submittal Review Notes |
| 6/5/2025 |
Point Review - Pre-submittal Review Notes |
| 6/16/2025 |
Point Review - Pre-submittal Review Notes |
| 6/21/2025 |
Point Review - Pre-submittal Review Notes |
| 6/23/2025 |
Point Review - Pre-submittal Review Notes |
| 7/5/2025 |
Point Review - Pre-submittal Review Notes |
| 7/10/2025 |
Point Review - Pre-submittal Review Notes |
| 7/11/2025 |
Point Review - Pre-submittal Review Notes |
| 7/12/2025 |
Point Review - Pre-submittal Review Notes |
| 7/17/2025 |
Point Review - Pre-submittal Review Notes |
| 7/20/2025 |
Point Review - Pre-submittal Review Notes |
| 7/23/2025 |
Point Review - Pre-submittal Review Notes |
| 7/29/2025 |
Point Review - Pre-submittal Review Notes |
| 8/4/2025 |
Point Review - Pre-submittal Review Notes |
| 8/5/2025 |
Point Review - Ready for applicant submittal |
| 8/6/2025 |
Point Review - Ready for applicant submittal |
| 8/12/2025 |
Point Review - Ready for applicant submittal |
| 8/13/2025 |
Application submitted by applicant. |
| 8/13/2025 |
Point Review - Reviewed |
| 8/13/2025 |
Zoning Review - Reviewed |
| 8/26/2025 |
Plan Review - Processing |
| 8/26/2025 |
Plan Review - Documents Required |
| 8/28/2025 |
Plan Review - Documents Required |
| 8/29/2025 |
Plan Review - Mechanical Approved |
| 8/29/2025 |
Plan Review - Plumbing Approved |
| 8/29/2025 |
Plan Review - Electrical Approved |
| 8/29/2025 |
Plan Review - Building Approved |
| 8/29/2025 |
Plan Review - Reviewed |
| 8/29/2025 |
Final Review - Processing |
| 9/1/2025 |
Final Review - Reviewed |
| 9/1/2025 |
Final Review - Payment Needed |
| 9/3/2025 |
Permit Issued |
| 4/10/2026 |
Permit Renewed |