| 6/18/2025 |
Application pending. |
| 6/18/2025 |
Application submitted by applicant. |
| 6/18/2025 |
City of Lake City Utilities Notified. |
| 6/18/2025 |
Point Review - Printed-Online Application |
| 6/25/2025 |
Zoning Review - Reviewed |
| 6/25/2025 |
Plan Review - Electrical Approved |
| 6/25/2025 |
Plan Review - Building Approved |
| 6/25/2025 |
Plan Review - Reviewed |
| 6/25/2025 |
Final Review - Processing |
| 6/30/2025 |
Final Review - Reviewed |
| 6/30/2025 |
Final Review - Payment Needed |
| 7/3/2025 |
Final Review - Payment Needed |
| 7/4/2025 |
Final Review - Payment Needed |
| 7/5/2025 |
Final Review - Payment Needed |
| 7/7/2025 |
Final Review - Payment Needed |
| 7/14/2025 |
Final Review - Payment Needed |
| 7/15/2025 |
Final Review - Payment Needed |
| 7/24/2025 |
Final Review - Payment Needed |
| 8/1/2025 |
Final Review - Payment Needed |
| 8/8/2025 |
Final Review - Payment Needed |
| 8/22/2025 |
Final Review - Payment Needed |
| 8/26/2025 |
Final Review - Payment Needed |
| 8/29/2025 |
Permit Issued |
| 9/25/2025 |
Permit Reissued |